Swaroop Grandeur, Andheri West

by Swaroop Constructions Private Limited · Andheri West, Mumbai 400053 · Map

Launched
Apr 20253 yrs 11 mths promised
Possession (MahaRERA)
Mar 2029Not extended
Concrete structure
6%Mid-construction
Booked (free sale)
32 of 5657% · 71 rehab units
Buildings
20.7 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale32 booked out of 56 units

Rehab71 units for existing members

Total 127 units. Rehab units are not for sale.

Project facts

2 BHK
116
Other units
11
Total units
127
Buildings
2
Land
0.7 acres
Phases
1
MahaRERA complaints
0
Free-sale units
56
Rehab units
71

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)6%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 90%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 4%Oct 2026: Concrete structure (RCC) 6%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 6%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%6%0%32
100%4%0%7
90%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400053

Projects with 50–250 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400053
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 11 mths4 yrs
Possession date extendedNo0 of 6
Possession date (MahaRERA)Mar 2029Mar 2029
Concrete structure (RCC)6%31%
Units booked (free sale)57%21%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Swaroop Grandeur by Swaroop Constructions Private Limited is a 127-unit BMC-sanctioned project in Andheri West, Mumbai 400053, launched in April 2025 with possession due in March 2029. 32 units booked out of 56 units for sale. The concrete structure (RCC) is 6% complete.

Read full summary

Swaroop Grandeur is a BMC-sanctioned project by Swaroop Constructions Private Limited in Andheri West, Mumbai 400053, registered with MahaRERA as P51800080127. It was launched in April 2025. It has 127 units in 2 buildings: 116 homes (2 BHK) and 11 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 127 units, 56 are for sale and 71 are rehab units for existing members.

Its registered possession date is March 2029, unchanged since launch. Construction: excavation complete, structure (RCC) 6% complete, final finishes not started.

32 units booked out of 56 units for sale (57%). Since the July 2026 update, 25 more units have been booked and the reported concrete structure (RCC) has gone from 4% to 6%.