Skip to main content

Trilok Heights, Andheri West

by Rashi Realty · Andheri West, Mumbai 400053 · Map

Launched
May 20253 yrs 7 mths promised
Possession (MahaRERA)
Dec 2028Not extended
Concrete structure
32%Mid-construction
Booked (free sale)
7 of 3321% · 25 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale7 booked out of 33 units

Rehab25 units for existing members

Total 58 units. Rehab units are not for sale.

Project facts

1 BHK
24
2 BHK
33
3 BHK
1
Total units
58
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
33
Rehab units
25

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)32%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 0%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 32%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 32%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%32%0%7
100%0%0%5
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400053

Projects with 20–150 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400053
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 7 mths3 yrs 8 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Dec 2028Mar 2029
Concrete structure (RCC)32%8%
Units booked (free sale)21%25%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Trilok Heights by Rashi Realty is a 58-unit SRA-sanctioned project in Andheri West, Mumbai 400053, launched in May 2025 with possession due in December 2028. 7 units booked out of 33 units for sale. The concrete structure (RCC) is 32% complete.

Read full summary

Trilok Heights is an SRA-sanctioned project by Rashi Realty in Andheri West, Mumbai 400053, registered with MahaRERA as PR1180002500058. It was launched in May 2025. It has 58 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 58 units, 33 are for sale and 25 are rehab units for existing members.

Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 32% complete, final finishes not started.

7 units booked out of 33 units for sale (21%). Since the July 2026 update, 2 more units have been booked and the reported concrete structure (RCC) has gone from 0% to 32%.