Skip to main content

Raghav Avenue, Chembur

by Raghav Raj Builders & Developers LLP · Chembur, Mumbai 400071 · Map

Launched
Mar 20254 yrs 3 mths promised
Possession (MahaRERA)
Jun 2029Not extended
Concrete structure
100%Nearing possession
Booked (free sale)
56 of 5798% · 29 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale56 booked out of 57 units

Rehab29 units for existing members

Total 86 units. Rehab units are not for sale.

Project facts

1 BHK
30
2 BHK
41
3 BHK
15
Total units
86
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
57
Rehab units
29

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 0%Jul 2026: Excavation 0%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 100%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 100%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%56
0%0%0%36
0%0%0%–

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400071

Projects with 40–200 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400071
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 3 mths3 yrs 10 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Jun 2029Dec 2028
Concrete structure (RCC)100%35%
Units booked (free sale)98%46%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Raghav Avenue by Raghav Raj Builders & Developers LLP is an 86-unit MHADA-sanctioned project in Chembur, Mumbai 400071, launched in March 2025 with possession due in June 2029. 56 units booked out of 57 units for sale. The concrete structure (RCC) is complete.

Read full summary

Raghav Avenue is a MHADA-sanctioned project by Raghav Raj Builders & Developers LLP in Chembur, Mumbai 400071, registered with MahaRERA as P51800079676. It was launched in March 2025. It has 86 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 86 units, 57 are for sale and 29 are rehab units for existing members.

Its registered possession date is June 2029, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes not started.

56 units booked out of 57 units for sale (98%). Since the July 2026 update, 20 more units have been booked and the reported concrete structure (RCC) has gone from 0% to 100%.