Rustomjee Balmoral, Chembur

by Keystone Realtors Limited · Chembur, Mumbai 400071 · Map

Launched
Apr 2025First of 4 phases
Possession (MahaRERA)
Apr 2030 – Dec 2030Not extended
Concrete structure
0%Weighted across 4 phases
Booked
16 of 11614% · 13 in Jul 2026
Buildings
44.2 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

3 BHK
54
4 BHK
58
5+ BHK
4
Total units
116
Buildings
4
Land
4.2 acres
Phases
4
MahaRERA complaints
1

The 4 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Rustomjee Balmoral - Wing D
Early stage
P51800079955360%11%
Rustomjee Balmoral - Wing F
Early stage
P51800080027360%14%
Rustomjee Balmoral - Wing A
Early stage
P51800080624360%11%
Rustomjee Balmoral - Wing C
Early stage
PR118000250211580%38%
Show updates by phase

Rustomjee Balmoral - Wing D (P51800079955)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%4
100%0%0%4
0%0%0%3

"–" means MahaRERA shows no figure for that update.

Rustomjee Balmoral - Wing F (P51800080027)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
90%0%0%5
0%0%0%5
0%0%0%0

"–" means MahaRERA shows no figure for that update.

Rustomjee Balmoral - Wing A (P51800080624)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%4
100%0%0%1
0%0%0%2

"–" means MahaRERA shows no figure for that update.

Rustomjee Balmoral - Wing C (PR1180002502115)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%3
100%0%0%3

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation97%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jul 2026Oct 2026Jul 2026: Excavation 69%Oct 2026: Excavation 97%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 97%Concrete structure (RCC) 0%Final finishes 0%

How to read construction stages

Compared with 6 similar projects in PIN 400071

Projects with 50–250 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400071
MeasureThis projectSimilar projects
Launch to possession (as first promised)5 yrs3 yrs 10 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Apr 2030 – Dec 2030Dec 2028
Concrete structure (RCC)0%92%
Units booked14%68%
MahaRERA complaints (filed by or against the builder)10

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Rustomjee Balmoral by Keystone Realtors Limited (Rustomjee) is a 116-unit BMC-sanctioned project in Chembur, Mumbai 400071, registered with MahaRERA in 4 phases, with possession dates from April 2030 to December 2030. 16 units booked out of total 116 units. Work on the concrete structure (RCC) has not started.

Read full summary

Rustomjee Balmoral is a BMC-sanctioned project by Keystone Realtors Limited in Chembur, Mumbai 400071, registered with MahaRERA as 4 phases (P51800079955, P51800080027, P51800080624, PR1180002502115). The first phase was launched in April 2025. Together the phases have 116 units in 4 buildings, with 3, 4 and 5+ BHK homes as registered with MahaRERA. All 4 phases are active on MahaRERA.

The phases' registered possession dates run from April 2030 to December 2030; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 0% complete and final finishes 0% complete. None of the 4 phases has its structure complete.

16 units booked out of total 116 units (14%). Since the July 2026 update, 3 more units have been booked.

Rustomjee's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA38
Total units across these projects3,435
Completed without extending the possession date15
Completed after an extension2
Lapsed5
Under construction16
Possession date extended on the builder's application8
Typical time from launch to 100% structure7 years 4 months
MahaRERA complaints (filed by or against the builder), all Rustomjee projects119 (11 of 38 projects)