Rustomjee Balmoral, Chembur
by Keystone Realtors Limited · Chembur, Mumbai 400071 · Map
- Launched
- Apr 2025First of 4 phases
- Possession (MahaRERA)
- Apr 2030 – Dec 2030Not extended
- Concrete structure
- 0%Weighted across 4 phases
- Booked
- 16 of 11614% · 13 in Jul 2026
- Buildings
- 44.2 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 3 BHK
- 54
- 4 BHK
- 58
- 5+ BHK
- 4
- Total units
- 116
- Buildings
- 4
- Land
- 4.2 acres
- Phases
- 4
- MahaRERA complaints
- 1
The 4 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Rustomjee Balmoral - Wing D Early stage | P51800079955 | 36 | 0% | 11% | |
| Rustomjee Balmoral - Wing F Early stage | P51800080027 | 36 | 0% | 14% | |
| Rustomjee Balmoral - Wing A Early stage | P51800080624 | 36 | 0% | 11% | |
| Rustomjee Balmoral - Wing C Early stage | PR1180002502115 | 8 | 0% | 38% |
Show updates by phase
Rustomjee Balmoral - Wing D (P51800079955)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 0% | 0% | 4 | |
| 100% | 0% | 0% | 4 | |
| 0% | 0% | 0% | 3 |
"–" means MahaRERA shows no figure for that update.
Rustomjee Balmoral - Wing F (P51800080027)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 90% | 0% | 0% | 5 | |
| 0% | 0% | 0% | 5 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Rustomjee Balmoral - Wing A (P51800080624)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 0% | 0% | 4 | |
| 100% | 0% | 0% | 1 | |
| 0% | 0% | 0% | 2 |
"–" means MahaRERA shows no figure for that update.
Rustomjee Balmoral - Wing C (PR1180002502115)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 0% | 0% | 3 | |
| 100% | 0% | 0% | 3 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Compared with 6 similar projects in PIN 400071
Projects with 50–250 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 5 yrs | 3 yrs 10 mths |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | Apr 2030 – Dec 2030 | Dec 2028 |
| Concrete structure (RCC) | 0% | 92% |
| Units booked | 14% | 68% |
| MahaRERA complaints (filed by or against the builder) | 1 | 0 |
The 6 projects
- Raghav Avenue, Chembur
- Eva Aspire, Chembur
- Vighnaharta Enclave, Chembur
- Sidhivinayak Aura, Chembur
- Casa Bella, Chembur
- Raghav Vista, Chembur
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Raghav Avenue | March 2025 | June 2029 | 100% | 56 units booked out of 57 units for sale |
| Eva Aspire | March 2025 | December 2027 | 100% | 102 units booked out of total 165 units |
| Vighnaharta Enclave | March 2025 | December 2028 | 0% | 45 units booked out of 134 units for sale |
| Sidhivinayak Aura | March 2025 | December 2027 | 85% | 15 units booked out of 20 units for sale |
| Casa Bella | July 2025 | June 2030 | 43% | 4 units booked out of 36 units for sale |
| Raghav Vista | December 2024 | December 2028 | 100% | 60 units booked out of 71 units for sale |
About this project
Rustomjee Balmoral by Keystone Realtors Limited (Rustomjee) is a 116-unit BMC-sanctioned project in Chembur, Mumbai 400071, registered with MahaRERA in 4 phases, with possession dates from April 2030 to December 2030. 16 units booked out of total 116 units. Work on the concrete structure (RCC) has not started.
Read full summary
Rustomjee Balmoral is a BMC-sanctioned project by Keystone Realtors Limited in Chembur, Mumbai 400071, registered with MahaRERA as 4 phases (P51800079955, P51800080027, P51800080624, PR1180002502115). The first phase was launched in April 2025. Together the phases have 116 units in 4 buildings, with 3, 4 and 5+ BHK homes as registered with MahaRERA. All 4 phases are active on MahaRERA.
The phases' registered possession dates run from April 2030 to December 2030; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 0% complete and final finishes 0% complete. None of the 4 phases has its structure complete.
16 units booked out of total 116 units (14%). Since the July 2026 update, 3 more units have been booked.
Rustomjee's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 38 |
|---|---|
| Total units across these projects | 3,435 |
| Completed without extending the possession date | 15 |
| Completed after an extension | 2 |
| Lapsed | 5 |
| Under construction | 16 |
| Possession date extended on the builder's application | 8 |
| Typical time from launch to 100% structure | 7 years 4 months |
| MahaRERA complaints (filed by or against the builder), all Rustomjee projects | 119 (11 of 38 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.