Ruparel Zinnia, Borivali West

by Ami Modispaces LLP · Borivali West, Mumbai 400092 · Map

Launched
Feb 20253 yrs 4 mths promised
Possession (MahaRERA)
Jun 2028Not extended
Concrete structure
81%Mid-construction
Booked
108 of 13381% · 97 in Jul 2026
Buildings
20.4 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
12
2 BHK
104
3 BHK
4
Other units
13
Total units
133
Buildings
2
Land
0.4 acres
Phases
1
MahaRERA complaints
1
Reserved units
56

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)81%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 18%Jul 2026: Concrete structure (RCC) 43%Oct 2026: Concrete structure (RCC) 81%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 81%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%81%0%108
100%43%0%97
100%18%0%81

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400092

Projects with 60–250 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400092
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 4 mths3 yrs 3 mths
Possession date extendedNo1 of 4
Possession date (MahaRERA)Jun 2028May 2028
Concrete structure (RCC)81%58%
Units booked81%43%
MahaRERA complaints (filed by or against the builder)10

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Ruparel Zinnia by Ami Modispaces LLP (Ruparel) is a 133-unit SRA-sanctioned project in Borivali West, Mumbai 400092, launched in February 2025 with possession due in June 2028. 108 units booked out of total 133 units. The concrete structure (RCC) is 81% complete.

Read full summary

Ruparel Zinnia is an SRA-sanctioned project by Ami Modispaces LLP in Borivali West, Mumbai 400092, registered with MahaRERA as P51800079098. It was launched in February 2025. It has 133 units in 2 buildings: 120 homes (1, 2 and 3 BHK) and 13 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is June 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 81% complete, final finishes not started.

108 units booked out of total 133 units (81%). Since the July 2026 update, 11 more units have been booked and the reported concrete structure (RCC) has gone from 43% to 81%.

Ruparel's track record in Mumbai

MahaRERA projects registered 2017–2025 in Mumbai

Projects registered with MahaRERA28
Total units across these projects6,570
Completed without extending the possession date0
Completed after an extension1
Lapsed12
Under construction15
Possession date extended on the builder's application14
Typical time from launch to 100% structure5 years 9 months
MahaRERA complaints (filed by or against the builder), all Ruparel projects872 (22 of 28 projects)

See all Ruparel projects →