Skip to main content

The Harvest, Chembur

by Bindu Raheja And Sons LLP · Chembur, Mumbai 400071 · Map

Launched
May 20253 yrs 1 mth promised
Possession (MahaRERA)
Jun 2028Not extended
Concrete structure
100%Nearing possession
Booked (free sale)
5 of 1729%
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale5 booked out of 17 units

Land-owner share12 units, not for sale

Total 29 units. Land-owner units are not for sale.

Project facts

2 BHK
13
3 BHK
12
Other units
4
Total units
29
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
17
Land-owner share (not for sale)
12

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services80%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 14%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2025: Final finishes 0%Jul 2026: Final finishes 50%Oct 2026: Final finishes 80%Excavation 100%Concrete structure (RCC) 100%Final finishes 80%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%80%5
100%100%50%2
100%14%0%2

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400071

Projects with 10–50 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 400071
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 1 mth2 yrs 7 mths
Possession date extendedNo0 of 5
Possession date (MahaRERA)Jun 2028Dec 2027
Concrete structure (RCC)100%100%
Units booked (free sale)29%86%
MahaRERA complaints (filed by or against the builder)00

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

The Harvest by Bindu Raheja And Sons LLP is a 29-unit BMC-sanctioned project in Chembur, Mumbai 400071, launched in May 2025 with possession due in June 2028. 5 units booked out of 17 units for sale. The concrete structure (RCC) is complete.

Read full summary

The Harvest is a BMC-sanctioned project by Bindu Raheja And Sons LLP in Chembur, Mumbai 400071, registered with MahaRERA as P51800080369. It was launched in May 2025. It has 29 units in 1 building: 25 homes (2 and 3 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 29 units, 17 are for sale and 12 are the land-owner's share, not for sale.

Its registered possession date is June 2028, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 80% complete.

5 units booked out of 17 units for sale (29%). Since the July 2026 update, 3 more units have been booked.