Vardhaman Ananda, Ghatkopar East

by Vardhaman Infra Realty Private Limited · Ghatkopar East, Mumbai 400077 · Map

Launched
Aug 20252 yrs 4 mths promised
Possession (MahaRERA)
Dec 2027Not extended
Concrete structure
60%Mid-construction
Booked (free sale)
0 of 70% · 7 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale0 booked out of 7 units

Rehab7 units for existing members

Total 14 units. Rehab units are not for sale.

Project facts

2 BHK
8
3 BHK
6
Total units
14
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
7
Rehab units
7

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)60%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 55%Oct 2026: Concrete structure (RCC) 60%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 60%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%60%0%0
100%55%0%0
100%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400077

Projects with up to 30 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 400077
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 4 mths2 yrs 4 mths
Possession date extendedNo0 of 3
Possession date (MahaRERA)Dec 2027Dec 2027
Concrete structure (RCC)60%92%
Units booked (free sale)0%33%
MahaRERA complaints (filed by or against the builder)00

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Vardhaman Ananda by Vardhaman Infra Realty Private Limited is a 14-unit BMC-sanctioned project in Ghatkopar East, Mumbai 400077, launched in August 2025 with possession due in December 2027. 0 units booked out of 7 units for sale. The concrete structure (RCC) is 60% complete.

Read full summary

Vardhaman Ananda is a BMC-sanctioned project by Vardhaman Infra Realty Private Limited in Ghatkopar East, Mumbai 400077, registered with MahaRERA as PR1180002500458. It was launched in August 2025. It has 14 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 14 units, 7 are for sale and 7 are rehab units for existing members.

Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 60% complete, final finishes not started.

0 units booked out of 7 units for sale (0%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 55% to 60%.