Surylok, Borivali West
by Mahavir Land Developer · Borivali West, Mumbai 400091 · Map
- Launched
- Jul 20254 yrs 5 mths promised
- Possession (MahaRERA)
- Dec 2029Not extended
- Concrete structure
- 20%Mid-construction
- Booked (free sale)
- 24 of 7632% · 60 rehab units
- Buildings
- 20.8 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale24 booked out of 76 units
Rehab60 units for existing members
Total 136 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 70
- 2 BHK
- 66
- Total units
- 136
- Buildings
- 2
- Land
- 0.8 acres
- Phases
- 1
- MahaRERA complaints
- 1
- Free-sale units
- 76
- Rehab units
- 60
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 20% | 0% | 24 | |
| 100% | 5% | 0% | 18 | |
| 30% | 0% | 0% | 1 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400091
Projects with 60–300 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs 5 mths | 3 yrs 8 mths |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | Dec 2029 | Jul 2029 |
| Concrete structure (RCC) | 20% | 16% |
| Units booked (free sale) | 32% | 15% |
| MahaRERA complaints (filed by or against the builder) | 1 | 0 |
The 6 projects
- Breeze 91, Borivali West
- Aurum, Borivali West
- Tulip Tower, Borivali West
- Kaustubh Capital, Borivali West
- Jalkirti CHS Ltd Redevelopment Project, Borivali West
- 25 Rbc, Borivali West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Breeze 91 | June 2025 | March 2030 | 65% | 54 units booked out of 61 units for sale |
| Aurum | June 2025 | June 2028 | 70% | 40 units booked out of 58 units for sale |
| Tulip Tower | August 2025 | June 2028 | 25% | 10 units booked out of 50 units for sale |
| Kaustubh Capital | December 2025 | September 2030 | 0% | 6 units booked out of 78 units for sale |
| Jalkirti CHS Ltd Redevelopment Project | December 2025 | December 2029 | 0% | 4 units booked out of 39 units for sale |
| 25 Rbc | December 2025 | March 2029 | 7% | 3 units booked out of 39 units for sale |
About this project
Surylok by Mahavir Land Developer is a 136-unit BMC-sanctioned project in Borivali West, Mumbai 400091, launched in July 2025 with possession due in December 2029. 24 units booked out of 76 units for sale. The concrete structure (RCC) is 20% complete.
Read full summary
Surylok is a BMC-sanctioned project by Mahavir Land Developer in Borivali West, Mumbai 400091, registered with MahaRERA as PR1181012500358. It was launched in July 2025. It has 136 units in 2 buildings, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 136 units, 76 are for sale and 60 are rehab units for existing members.
Its registered possession date is December 2029, unchanged since launch. Construction: excavation complete, structure (RCC) 20% complete, final finishes not started.
24 units booked out of 76 units for sale (32%). Since the July 2026 update, 6 more units have been booked and the reported concrete structure (RCC) has gone from 5% to 20%.