Tulip Tower, Borivali West
by Hem Builders And Developers · Borivali West, Mumbai 400091 · Map
- Launched
- Aug 20252 yrs 10 mths promised
- Possession (MahaRERA)
- Jun 2028Not extended
- Concrete structure
- 25%Mid-construction
- Booked (free sale)
- 10 of 5020% · 16 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale10 booked out of 50 units
Rehab16 units for existing members
Total 66 units. Rehab units are not for sale.
Project facts
- 2 BHK
- 32
- 3 BHK
- 28
- Other units
- 6
- Total units
- 66
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 50
- Rehab units
- 16
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 25% | 0% | 10 | |
| 100% | 5% | 0% | – | |
| 30% | 0% | 0% | – |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400091
Projects with 30–150 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 10 mths | 3 yrs 4 mths |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | Jun 2028 | Nov 2028 |
| Concrete structure (RCC) | 25% | 48% |
| Units booked (free sale) | 20% | 65% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Surylok, Borivali West
- Rls 280, Borivali West
- Aurum, Borivali West
- Shilp Sangeet Co-Op Housing Society Ltd, Borivali West
- Breeze 91, Borivali West
- Gorai Samadhan Cooperative Housing Society Limited, Borivali West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Surylok | July 2025 | December 2029 | 20% | 24 units booked out of 76 units for sale |
| Rls 280 | June 2025 | March 2029 | 0% | 29 units booked out of 48 units for sale |
| Aurum | June 2025 | June 2028 | 70% | 40 units booked out of 58 units for sale |
| Shilp Sangeet Co-Op Housing Society Ltd | June 2025 | March 2028 | 100% | 10 units booked out of 18 units for sale |
| Breeze 91 | June 2025 | March 2030 | 65% | 54 units booked out of 61 units for sale |
| Gorai Samadhan Cooperative Housing Society Limited | December 2025 | June 2027 | 30% | 28 units booked out of 28 units for sale |
About this project
Tulip Tower by Hem Builders And Developers is a 66-unit MHADA-sanctioned project in Borivali West, Mumbai 400091, launched in August 2025 with possession due in June 2028. 10 units booked out of 50 units for sale. The concrete structure (RCC) is 25% complete.
Read full summary
Tulip Tower is a MHADA-sanctioned project by Hem Builders And Developers in Borivali West, Mumbai 400091, registered with MahaRERA as PM1180002500631. It was launched in August 2025. It has 66 units in 1 building: 60 homes (2 and 3 BHK) and 6 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 66 units, 50 are for sale and 16 are rehab units for existing members.
Its registered possession date is June 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 25% complete, final finishes not started.
10 units booked out of 50 units for sale (20%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 5% to 25%.