Garden Palacio, Ghatkopar East

by Maple Avenues LLP · Ghatkopar East, Mumbai 400077 · Map

Launched
Aug 20252 yrs 4 mths promised
Possession (MahaRERA)
Dec 2027Not extended
Concrete structure
100%Nearing possession
Booked (free sale)
3 of 933% · 9 rehab units
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale3 booked out of 9 units

Rehab9 units for existing members

Total 18 units. Rehab units are not for sale.

Project facts

1 BHK
2
2 BHK
8
3 BHK
8
Total units
18
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
9
Rehab units
9

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 0%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 11%Oct 2026: Concrete structure (RCC) 100%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 100%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%3
100%11%0%1
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400077

Projects with up to 40 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400077
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 4 mths2 yrs 6 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Dec 2027Mar 2028
Concrete structure (RCC)100%60%
Units booked (free sale)33%24%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Garden Palacio by Maple Avenues LLP is an 18-unit BMC-sanctioned project in Ghatkopar East, Mumbai 400077, launched in August 2025 with possession due in December 2027. 3 units booked out of 9 units for sale. The concrete structure (RCC) is complete.

Read full summary

Garden Palacio is a BMC-sanctioned project by Maple Avenues LLP in Ghatkopar East, Mumbai 400077, registered with MahaRERA as PR1180002500510. It was launched in August 2025. It has 18 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 18 units, 9 are for sale and 9 are rehab units for existing members.

Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes not started.

3 units booked out of 9 units for sale (33%). Since the July 2026 update, 2 more units have been booked and the reported concrete structure (RCC) has gone from 11% to 100%.