Shree Sai Mauli, Mahim
by Dilip Shriniwas Hate · Mahim, Mumbai 400016 · Map
- Launched
- Aug 201710 yrs 4 mths promised
- Possession (MahaRERA)
- Dec 2027Not extended
- Concrete structure
- 60%Mid-construction
- Booked (free sale)
- 10 of 1283% · 21 rehab units
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale10 booked out of 12 units
Rehab21 units for existing members
Land-owner share3 units, not for sale
Total 36 units. Rehab and land-owner units are not for sale.
Project facts
- 1 BHK
- 22
- 2 BHK
- 6
- 3 BHK
- 8
- Total units
- 36
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 12
- Rehab units
- 21
- Land-owner share (not for sale)
- 3
- Reserved units
- 4
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 60% | 10% | 10 | |
| 100% | 56% | 0% | 10 | |
| 100% | 56% | 0% | 10 | |
| 100% | 35% | 0% | 4 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400016
Projects with 10–80 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 10 yrs 4 mths | 5 yrs 2 mths |
| Possession date extended | No | 4 of 6 |
| Possession date (MahaRERA) | Dec 2027 | Mar 2024 |
| Concrete structure (RCC) | 60% | 100% |
| Units booked (free sale) | 83% | 41% |
| MahaRERA complaints (filed by or against the builder) | 0 | 5 |
The 6 projects
- Mehrabad, Mahim
- Shristi Sea View, Mahim
- Tridhaatu Kshitij, Mahim
- Ruparel Iris, Mahim
- Rajkamal Building, Mahim
- Mama Heights, Mahim
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Mehrabad | August 2017 | December 2025 | 100% | 14 units booked out of total 48 units |
| Shristi Sea View | August 2017 | December 2023 | 66% | 37 units booked out of total 49 units |
| Tridhaatu Kshitij | August 2017 | December 2023 | 100% | 34 units booked out of total 66 units |
| Ruparel Iris | August 2017 | June 2024 | 100% | 30 units booked out of total 98 units |
| Rajkamal Building | September 2017 | October 2022 | 0% | 4 units booked out of total 31 units |
| Mama Heights | July 2017 | April 2025 | 100% | 51 units booked out of 72 units for sale |
About this project
Shree Sai Mauli by Dilip Shriniwas Hate is a 36-unit BMC-sanctioned project in Mahim, Mumbai 400016, launched in August 2017 with possession due in December 2027. 10 units booked out of 12 units for sale. The concrete structure (RCC) is 60% complete.
Read full summary
Shree Sai Mauli is a BMC-sanctioned project by Dilip Shriniwas Hate in Mahim, Mumbai 400016, registered with MahaRERA as P51900002897. It was launched in August 2017. It has 36 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 36 units, 12 are for sale, 21 are rehab units for existing members and 3 are the land-owner's share, not for sale.
Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 60% complete, final finishes 10% complete.
10 units booked out of 12 units for sale (83%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 56% to 60%.