Rajkamal Building, Mahim

Lapsed

by J.P. Porwal Realty · Mahim, Mumbai 400016 · Map

Launched
Sep 20175 yrs 1 mth promised
Possession (MahaRERA)
Oct 2022Not extendedWhat does Lapsed mean?
Concrete structure
0%Early stage
Booked
4 of 3113%
Buildings
10.2 acres
MahaRERA complaints
3Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
12
3 BHK
15
4 BHK
1
5+ BHK
1
Other units
2
Total units
31
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
3

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%4
100%0%0%–
100%0%0%–
100%0%0%4

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400016

Projects with 10–60 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 400016
MeasureThis projectSimilar projects
Launch to possession (as first promised)5 yrs 1 mth5 yrs 4 mths
Possession date extendedNo2 of 3
Possession date (MahaRERA)Oct 2022Dec 2025
Concrete structure (RCC)0%66%
Units booked13%76%
MahaRERA complaints (filed by or against the builder)30

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Rajkamal Building by J.P. Porwal Realty is a 31-unit project in Mahim, Mumbai 400016, launched in September 2017; its MahaRERA registration has lapsed. 4 units booked out of total 31 units. Work on the concrete structure (RCC) has not started.

Read full summary

Rajkamal Building is a project by J.P. Porwal Realty in Mahim, Mumbai 400016, registered with MahaRERA as P51900012757. It was launched in September 2017. It has 31 units in 1 building: 29 homes (2, 3, 4 and 5+ BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in October 2022. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) not started, final finishes not started.

4 units booked out of total 31 units (13%).