Shristi Sea View, Mahim

Lapsed

by Avarsekar Realty Pvt Ltd · Mahim, Mumbai 400016 · Map

Launched
Aug 20172 yrs 4 mths originally promised
Possession (MahaRERA)
Dec 2023Extended by 4 yrsWhat does Lapsed mean?
Concrete structure
66%Mid-construction
Booked
37 of 4976%
Buildings
10.8 acres
MahaRERA complaints
8Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
2
3 BHK
44
4 BHK
3
Total units
49
Buildings
1
Land
0.8 acres
Phases
1
MahaRERA complaints
8

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)66%
Finishes, lifts and services30%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 66%Dec 2025: Concrete structure (RCC) 66%Jul 2026: Concrete structure (RCC) 66%Oct 2026: Concrete structure (RCC) 66%Dec 2024: Final finishes 30%Dec 2025: Final finishes 30%Jul 2026: Final finishes 30%Oct 2026: Final finishes 30%Excavation 100%Concrete structure (RCC) 66%Final finishes 30%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%66%30%37
100%66%30%–
100%66%30%–
100%66%30%37

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400016

Projects with 20–100 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400016
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 4 mths5 yrs 10 mths
Possession date extendedBy 4 yrs3 of 6
Possession date (MahaRERA)Dec 2023Nov 2024
Concrete structure (RCC)66%100%
Units booked76%41%
MahaRERA complaints (filed by or against the builder)82

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Shristi Sea View by Avarsekar Realty Pvt Ltd is a 49-unit project in Mahim, Mumbai 400016, launched in August 2017; its MahaRERA registration has lapsed. 37 units booked out of total 49 units. The concrete structure (RCC) is 66% complete.

Read full summary

Shristi Sea View is a project by Avarsekar Realty Pvt Ltd in Mahim, Mumbai 400016, registered with MahaRERA as P51900002867. It was launched in August 2017. It has 49 units in 1 building, with 1, 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2023, after an extension of 4 years from the original December 2019. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 66% complete, final finishes 30% complete.

37 units booked out of total 49 units (76%).