Promesa West End, Dadar West

Ready to move

by M/s. virtue Enterprises · Dadar West, Mumbai 400028 · Map

Launched
Aug 20174 yrs 4 mths originally promised
Possession (MahaRERA)
Dec 2026Extended by 5 yrs
Concrete structure
100%Ready to move
Booked (free sale)
35 of 6157% · 69 rehab units
Buildings
10.2 acres
MahaRERA complaints
3Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale35 booked out of 61 units

Rehab69 units for existing members

Total 130 units. Rehab units are not for sale.

Project facts

2 BHK
126
Other units
4
Total units
130
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
3
Free-sale units
61
Rehab units
69

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services100%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 0%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 60%Oct 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%35
100%100%60%35
0%0%0%–
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400028

Projects with 60–300 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400028
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 4 mths4 yrs 4 mths
Possession date extendedBy 5 yrs4 of 4
Possession date (MahaRERA)Dec 2026May 2023
Concrete structure (RCC)100%100%
MahaRERA complaints (filed by or against the builder)31

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Promesa West End by M/s. virtue Enterprises is a 130-unit BMC-sanctioned project in Dadar West, Mumbai 400028, launched in August 2017 with possession due in December 2026. 35 units booked out of 61 units for sale. The concrete structure (RCC) is complete.

Read full summary

Promesa West End is a BMC-sanctioned project by M/s. virtue Enterprises in Dadar West, Mumbai 400028, registered with MahaRERA as P51900004931. It was launched in August 2017. It has 130 units in 1 building: 126 homes (2 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 130 units, 61 are for sale and 69 are rehab units for existing members.

Its registered possession date is December 2026, extended by 5 years from the original December 2021. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.

35 units booked out of 61 units for sale (57%).