Neha Galaxy, Dadar West

Lapsed

by Shishir Mangeh Shivapurkar · Dadar West, Mumbai 400028 · Map

Launched
Aug 20173 yrs 9 mths originally promised
Possession (MahaRERA)
May 2022Extended by 1 yrWhat does Lapsed mean?
Concrete structure
100%Nearing possession
Booked (free sale)
14 of 2070% · 58 rehab units
Buildings
10.1 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale14 booked out of 20 units

Rehab58 units for existing members

Land-owner share4 units, not for sale

Total 82 units. Rehab and land-owner units are not for sale.

Project facts

1 BHK
62
3 BHK
10
Other units
10
Total units
82
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
1
Free-sale units
20
Rehab units
58
Land-owner share (not for sale)
4

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services60%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 60%Dec 2025: Final finishes 60%Jul 2026: Final finishes 60%Excavation 100%Concrete structure (RCC) 100%Final finishes 60%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%60%14
100%100%60%14
100%100%60%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400028

Projects with 30–150 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 400028
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 9 mths4 yrs 4 mths
Possession date extendedBy 1 yr5 of 5
Possession date (MahaRERA)May 2022Dec 2025
Concrete structure (RCC)100%100%
Units booked (free sale)70%89%
MahaRERA complaints (filed by or against the builder)11

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Neha Galaxy by Shishir Mangeh Shivapurkar is an 82-unit BMC-sanctioned project in Dadar West, Mumbai 400028, launched in August 2017; its MahaRERA registration has lapsed. 14 units booked out of 20 units for sale. The concrete structure (RCC) is complete.

Read full summary

Neha Galaxy is a BMC-sanctioned project by Shishir Mangeh Shivapurkar in Dadar West, Mumbai 400028, registered with MahaRERA as P51900010851. It was launched in August 2017. It has 82 units in 1 building: 72 homes (1 and 3 BHK) and 10 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 82 units, 20 are for sale, 58 are rehab units for existing members and 4 are the land-owner's share, not for sale.

Possession was due in May 2022, after an extension of 1 year from the original May 2021. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 60% complete.

14 units booked out of 20 units for sale (70%).