Ocean Star, Dadar West

by Suraj Estate Developers Ltd · Dadar West, Mumbai 400028 · Map

Launched
Aug 2017First of 2 phases
Possession (MahaRERA)
Aug 2019 – Mar 2027Extended in both phases
Concrete structure
93%Weighted across 2 phases
Booked (free sale)
–
Buildings
20.3 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale73 units; booked –

Rehab18 units for existing members

Land-owner share6 units, not for sale

Total 97 units. Rehab and land-owner units are not for sale.

Project facts

1 BHK
36
2 BHK
4
3 BHK
52
4 BHK
4
Other units
1
Total units
97
Buildings
2
Land
0.3 acres
Phases
2
MahaRERA complaints
1
Free-sale units
73
Rehab units
18
Land-owner share (not for sale)
6

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Ocean Star I
Mid-construction
P519000072576690%58%
Ocean Star II
Ready to move Lapsed
P5190000777730100%–
Show updates by phase

Ocean Star I (P51900007257)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%90%5%39
100%90%0%39
100%90%0%–
100%90%0%33

"–" means MahaRERA shows no figure for that update.

Ocean Star II (P51900007777)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%–
100%100%100%–
100%100%100%30

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)93%
Finishes, lifts and services35%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 93%Dec 2025: Concrete structure (RCC) 93%Jul 2026: Concrete structure (RCC) 93%Oct 2026: Concrete structure (RCC) 93%Dec 2024: Final finishes 31%Dec 2025: Final finishes 31%Jul 2026: Final finishes 31%Oct 2026: Final finishes 35%Excavation 100%Concrete structure (RCC) 93%Final finishes 35%

How to read construction stages

Compared with 3 similar projects in PIN 400028

Projects with 40–200 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 400028
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 5 mths4 yrs 4 mths
Possession date extendedYes3 of 3
Possession date (MahaRERA)Aug 2019 – Mar 2027Dec 2025
Concrete structure (RCC)93%100%
Units booked (free sale)–70%
MahaRERA complaints (filed by or against the builder)11

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Ocean Star by Suraj Estate Developers Ltd is a 97-unit BMC-sanctioned project in Dadar West, Mumbai 400028, registered with MahaRERA in 2 phases, with possession dates from August 2019 to March 2027. The concrete structure (RCC) is 93% complete.

Read full summary

Ocean Star is a BMC-sanctioned project by Suraj Estate Developers Ltd in Dadar West, Mumbai 400028, registered with MahaRERA as 2 phases (P51900007257, P51900007777). The first phase was launched in August 2017. Together the phases have 97 units in 2 buildings: 96 homes (1, 2, 3 and 4 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. On MahaRERA, 1 is active and 1 is lapsed. Of the 97 units, 73 are for sale, 18 are rehab units for existing members and 6 are the land-owner's share, not for sale.

The phases' registered possession dates run from August 2019 to March 2027; both phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 93% complete and final finishes 35% complete. Neither phase has its structure complete.

Suraj Estate's track record in Mumbai

MahaRERA projects registered 2017–2025 in Mumbai

Projects registered with MahaRERA17
Total units across these projects1,217
Completed without extending the possession date0
Completed after an extension4
Lapsed3
Under construction10
Possession date extended on the builder's application10
Typical time from launch to 100% structure7 years 4 months
MahaRERA complaints (filed by or against the builder), all Suraj Estate projects11 (6 of 17 projects)

See all Suraj Estate projects →