- Launched
- Aug 20176 yrs 4 mths originally promised
- Possession (MahaRERA)
- Dec 2025Extended by 2 yrsWhat does Lapsed mean?
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 117 of 12494% · 25 rehab units
- Buildings
- 10.8 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale117 booked out of 124 units
Rehab25 units for existing members
Total 149 units. Rehab units are not for sale.
Project facts
- 1 RK
- 9
- 1 BHK
- 59
- 2 BHK
- 29
- 3 BHK
- 43
- 4 BHK
- 1
- Other units
- 8
- Total units
- 149
- Buildings
- 1
- Land
- 0.8 acres
- Phases
- 1
- MahaRERA complaints
- 1
- Free-sale units
- 124
- Rehab units
- 25
- Reserved units
- 55
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 68% | 117 | |
| 100% | 100% | 5% | 117 | |
| 100% | 81% | 4% | 17 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400028
Projects with 70–300 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 6 yrs 4 mths | 3 yrs 9 mths |
| Possession date extended | By 2 yrs | 3 of 3 |
| Possession date (MahaRERA) | Dec 2025 | May 2022 |
| Concrete structure (RCC) | 100% | 100% |
| MahaRERA complaints (filed by or against the builder) | 1 | 1 |
The 3 projects
- Promesa West End, Dadar West
- Ocean Star, Dadar West
- Neha Galaxy, Dadar West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Promesa West End | August 2017 | December 2026 | 100% | 35 units booked out of 61 units for sale |
| Ocean Star | August 2017 | Aug 2019 – Mar 2027 | 93% | – |
| Neha Galaxy | August 2017 | May 2022 | 100% | 14 units booked out of 20 units for sale |
About this project
Eon One by Firstlight Properties Private Limited is a 149-unit BMC-sanctioned project in Dadar West, Mumbai 400028, launched in August 2017; its MahaRERA registration has lapsed. 117 units booked out of 124 units for sale. The concrete structure (RCC) is complete.
Read full summary
Eon One is a BMC-sanctioned project by Firstlight Properties Private Limited in Dadar West, Mumbai 400028, registered with MahaRERA as P51900011726. It was launched in August 2017. It has 149 units in 1 building: 141 homes (1 RK, 1 BHK, 2 BHK, 3 BHK and 4 BHK) and 8 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 149 units, 124 are for sale and 25 are rehab units for existing members.
Possession was due in December 2025, after an extension of 2 years from the original December 2023. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 68% complete.
117 units booked out of 124 units for sale (94%).