- Launched
- Aug 20175 yrs 4 mths promised
- Possession (MahaRERA)
- Dec 2022Not extendedWhat does Lapsed mean?
- Concrete structure
- 0%Early stage
- Booked
- 2 of 1118%
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 3
- 2 BHK
- 8
- Total units
- 11
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 0% | 0% | 2 | |
| 100% | 0% | 0% | – | |
| 100% | 0% | 0% | – | |
| 100% | 0% | 0% | 2 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400028
Projects with up to 30 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 5 yrs 4 mths | 2 yrs 8 mths |
| Possession date extended | No | 3 of 3 |
| Possession date (MahaRERA) | Dec 2022 | Dec 2023 |
| Concrete structure (RCC) | 0% | 90% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- Santosh Building, Dadar West
- Om Heights, Dadar West
- Vipin Residency, Dadar West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Santosh Building | August 2017 | December 2021 | 50% | – |
| Om Heights | August 2017 | December 2026 | 100% | 6 units booked out of 13 units for sale |
| Vipin Residency | August 2017 | December 2023 | 90% | 18 units booked out of total 29 units |
About this project
Shaanti Ashish by Ruparel Estates India Pvt Ltd is an 11-unit project in Dadar West, Mumbai 400028, launched in August 2017; its MahaRERA registration has lapsed. 2 units booked out of total 11 units. Work on the concrete structure (RCC) has not started.
Read full summary
Shaanti Ashish is a project by Ruparel Estates India Pvt Ltd in Dadar West, Mumbai 400028, registered with MahaRERA as P51900007789. It was launched in August 2017. It has 11 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in December 2022. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) not started, final finishes not started.
2 units booked out of total 11 units (18%).
Ruparel's track record in Mumbai
MahaRERA projects registered 2017–2025 in Mumbai
| Projects registered with MahaRERA | 28 |
|---|---|
| Total units across these projects | 6,570 |
| Completed without extending the possession date | 0 |
| Completed after an extension | 1 |
| Lapsed | 12 |
| Under construction | 15 |
| Possession date extended on the builder's application | 14 |
| Typical time from launch to 100% structure | 5 years 9 months |
| MahaRERA complaints (filed by or against the builder), all Ruparel projects | 872 (22 of 28 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.