Shaanti Ashish, Dadar West

Lapsed

by Ruparel Estates India Pvt Ltd · Dadar West, Mumbai 400028 · Map

Launched
Aug 20175 yrs 4 mths promised
Possession (MahaRERA)
Dec 2022Not extendedWhat does Lapsed mean?
Concrete structure
0%Early stage
Booked
2 of 1118%
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
3
2 BHK
8
Total units
11
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%2
100%0%0%–
100%0%0%–
100%0%0%2

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400028

Projects with up to 30 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 400028
MeasureThis projectSimilar projects
Launch to possession (as first promised)5 yrs 4 mths2 yrs 8 mths
Possession date extendedNo3 of 3
Possession date (MahaRERA)Dec 2022Dec 2023
Concrete structure (RCC)0%90%
MahaRERA complaints (filed by or against the builder)00

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Shaanti Ashish by Ruparel Estates India Pvt Ltd is an 11-unit project in Dadar West, Mumbai 400028, launched in August 2017; its MahaRERA registration has lapsed. 2 units booked out of total 11 units. Work on the concrete structure (RCC) has not started.

Read full summary

Shaanti Ashish is a project by Ruparel Estates India Pvt Ltd in Dadar West, Mumbai 400028, registered with MahaRERA as P51900007789. It was launched in August 2017. It has 11 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2022. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) not started, final finishes not started.

2 units booked out of total 11 units (18%).

Ruparel's track record in Mumbai

MahaRERA projects registered 2017–2025 in Mumbai

Projects registered with MahaRERA28
Total units across these projects6,570
Completed without extending the possession date0
Completed after an extension1
Lapsed12
Under construction15
Possession date extended on the builder's application14
Typical time from launch to 100% structure5 years 9 months
MahaRERA complaints (filed by or against the builder), all Ruparel projects872 (22 of 28 projects)

See all Ruparel projects →