- Launched
- Aug 20175 yrs 4 mths originally promised
- Possession (MahaRERA)
- Dec 2023Extended by 1 yrWhat does Lapsed mean?
- Concrete structure
- 100%Ready to move
- Booked
- –
- Buildings
- 11.2 acres
- MahaRERA complaints
- 3Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 101
- 3 BHK
- 74
- Total units
- 175
- Buildings
- 1
- Land
- 1.2 acres
- Phases
- 1
- MahaRERA complaints
- 3
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 95% | – | |
| 100% | 100% | 95% | – | |
| 100% | 95% | 90% | 164 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400012
Projects with 80–350 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 5 yrs 4 mths | 4 yrs 4 mths |
| Possession date extended | By 1 yr | 3 of 3 |
| Possession date (MahaRERA) | Dec 2023 | Apr 2027 |
| Concrete structure (RCC) | 100% | 75% |
| MahaRERA complaints (filed by or against the builder) | 3 | 4 |
The 3 projects
- Ruparel Jewel, Parel
- Lifescapes Glory, Parel
- Chandra Darshan Heights, Parel
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Ruparel Jewel | August 2017 | April 2027 | 73% | 99 units booked out of total 191 units |
| Lifescapes Glory | August 2017 | October 2027 | 75% | 43 units booked out of 60 units for sale |
| Chandra Darshan Heights | September 2017 | Mar 2027 | 100% | – |
About this project
Nirvana Part I by Runwal Developers Ltd is a 175-unit BMC-sanctioned project in Parel, Mumbai 400012, launched in August 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is complete.
Read full summary
Nirvana Part I is a BMC-sanctioned project by Runwal Developers Ltd in Parel, Mumbai 400012, registered with MahaRERA as P51900010100. It was launched in August 2017. It has 175 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in December 2023, after an extension of 1 year from the original December 2022. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 95% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
Runwal's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 46 |
|---|---|
| Total units across these projects | 14,623 |
| Completed without extending the possession date | 10 |
| Completed after an extension | 5 |
| Lapsed | 5 |
| Under construction | 26 |
| Possession date extended on the builder's application | 16 |
| Typical time from launch to 100% structure | 7 years 4 months |
| MahaRERA complaints (filed by or against the builder), all Runwal projects | 343 (35 of 46 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.