Chandra Darshan Heights, Parel

by Commercial Developers · Parel, Mumbai 400012 · Map

Launched
Sep 2017First of 2 phases
Possession (MahaRERA)
Mar 2027Extended in 1 of 2 phases
Concrete structure
100%Weighted across 2 phases
Booked
–
Buildings
20.4 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 RK
3
1 BHK
81
2 BHK
27
Total units
111
Buildings
2
Land
0.4 acres
Phases
2
MahaRERA complaints
1
Reserved units
15

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Chandra Darshan Heights
Completed
P5190001192648100%–
Chandra Darshan Heights
Nearing possession
P5190005410563100%59%
Show updates by phase

Chandra Darshan Heights (P51900011926)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%–
100%100%100%–
100%100%100%16

"–" means MahaRERA shows no figure for that update.

Chandra Darshan Heights (P51900054105)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
70%100%75%37
70%100%60%33
70%85%0%22
70%95%0%0

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation83%
Concrete structure (slabs)100%
Finishes, lifts and services86%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 83%Dec 2025: Excavation 83%Jul 2026: Excavation 83%Oct 2026: Excavation 83%Dec 2024: Concrete structure (RCC) 97%Dec 2025: Concrete structure (RCC) 91%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 43%Dec 2025: Final finishes 43%Jul 2026: Final finishes 77%Oct 2026: Final finishes 86%Concrete structure (RCC) 100%Final finishes 86%Excavation 83%

How to read construction stages

Compared with 6 similar projects in PIN 400012

Projects with 50–250 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400012
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 3 mths5 yrs 4 mths
Possession date extendedYes6 of 6
Possession date (MahaRERA)Mar 2027Feb 2026
Concrete structure (RCC)100%100%
Units booked–75%
MahaRERA complaints (filed by or against the builder)12

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Chandra Darshan Heights by Commercial Developers is a 111-unit SRA-sanctioned project in Parel, Mumbai 400012, registered with MahaRERA in 2 phases, with possession due in March 2027. The concrete structure (RCC) is complete.

Read full summary

Chandra Darshan Heights is an SRA-sanctioned project by Commercial Developers in Parel, Mumbai 400012, registered with MahaRERA as 2 phases (P51900011926, P51900054105). The first phase was launched in September 2017. Together the phases have 111 units in 2 buildings, with 1 RK, 1 BHK and 2 BHK homes as registered with MahaRERA. On MahaRERA, 1 is completed and 1 is active.

The registered possession date is March 2027; 1 of 2 phases has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 86% complete. Both phases have their structure complete.