Sanghvi Estella, Parel

by Shree Naminath Lifespace LLP · Parel, Mumbai 400012 · Map

Launched
Sep 20176 yrs 3 mths originally promised
Possession (MahaRERA)
Apr 2027Extended by 3 yrs 4 mths
Concrete structure
100%Nearing possession
Booked
41 of 5575%
Buildings
10.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
16
2 BHK
38
3 BHK
1
Total units
55
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services80%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 80%Dec 2025: Final finishes 80%Jul 2026: Final finishes 80%Oct 2026: Final finishes 80%Excavation 100%Concrete structure (RCC) 100%Final finishes 80%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%80%41
100%100%80%41
100%100%80%41
100%100%80%33

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400012

Projects with 20–150 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400012
MeasureThis projectSimilar projects
Launch to possession (as first promised)6 yrs 3 mths4 yrs 4 mths
Possession date extendedBy 3 yrs 4 mths6 of 6
Possession date (MahaRERA)Apr 2027May 2026
Concrete structure (RCC)100%100%
Units booked75%100%
MahaRERA complaints (filed by or against the builder)01

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Sanghvi Estella by Shree Naminath Lifespace LLP is a 55-unit BMC-sanctioned project in Parel, Mumbai 400012, launched in September 2017 with possession due in April 2027. 41 units booked out of total 55 units. The concrete structure (RCC) is complete.

Read full summary

Sanghvi Estella is a BMC-sanctioned project by Shree Naminath Lifespace LLP in Parel, Mumbai 400012, registered with MahaRERA as P51900012022. It was launched in September 2017. It has 55 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is April 2027, extended by 3 years 4 months from the original December 2023. Construction: excavation complete, structure (RCC) complete, final finishes 80% complete.

41 units booked out of total 55 units (75%).