Skip to main content

Prarthana Grand, Parel

Lapsed

by Ojus Developers · Parel, Mumbai 400012 · Map

Launched
Aug 20171 yr 4 mths originally promised
Possession (MahaRERA)
Dec 2024Extended by 6 yrsWhat does Lapsed mean?
Concrete structure
100%Nearing possession
Booked
68 of 68100% · 0 in Jul 2026
Buildings
21.4 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
19
2 BHK
27
3 BHK
22
Total units
68
Buildings
2
Land
1.4 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services81%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 81%Dec 2025: Final finishes 81%Jul 2026: Final finishes 81%Oct 2026: Final finishes 81%Excavation 100%Concrete structure (RCC) 100%Final finishes 81%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%81%68
100%100%81%0
100%100%81%–
100%100%81%67

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400012

Projects with 30–150 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400012
MeasureThis projectSimilar projects
Launch to possession (as first promised)1 yr 4 mths5 yrs 4 mths
Possession date extendedBy 6 yrs6 of 6
Possession date (MahaRERA)Dec 2024Mar 2027
Concrete structure (RCC)100%100%
Units booked100%97%
MahaRERA complaints (filed by or against the builder)11

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Prarthana Grand by Ojus Developers is a 68-unit SRA-sanctioned project in Parel, Mumbai 400012, launched in August 2017; its MahaRERA registration has lapsed. 68 units booked out of total 68 units. The concrete structure (RCC) is complete.

Read full summary

Prarthana Grand is an SRA-sanctioned project by Ojus Developers in Parel, Mumbai 400012, registered with MahaRERA as P51900008215. It was launched in August 2017. It has 68 units in 2 buildings, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2024, after an extension of 6 years from the original December 2018. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 81% complete.

68 units booked out of total 68 units (100%). Since the July 2026 update, 68 more units have been booked and the possession date has moved from June 2020 to December 2024.