Skip to main content

Maruti Palatial, Parel

Ready to moveLapsed

by Grs Shelters Private Limited · Parel, Mumbai 400012 · Map

Launched
Aug 20176 yrs 4 mths originally promised
Possession (MahaRERA)
Dec 2024Extended by 1 yrWhat does Lapsed mean?
Concrete structure
100%Ready to move
Booked
58 of 6097%
Buildings
30.4 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
12
2 BHK
33
3 BHK
7
Other units
8
Total units
60
Buildings
3
Land
0.4 acres
Phases
1
MahaRERA complaints
1
Reserved units
4

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services97%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 97%Dec 2025: Final finishes 97%Jul 2026: Final finishes 97%Oct 2026: Final finishes 97%Excavation 100%Concrete structure (RCC) 100%Final finishes 97%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%97%58
100%100%97%58
100%100%97%58
100%100%97%58

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400012

Projects with 20–150 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400012
MeasureThis projectSimilar projects
Launch to possession (as first promised)6 yrs 4 mths4 yrs 4 mths
Possession date extendedBy 1 yr6 of 6
Possession date (MahaRERA)Dec 2024Mar 2027
Concrete structure (RCC)100%100%
Units booked97%100%
MahaRERA complaints (filed by or against the builder)11

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Maruti Palatial by Grs Shelters Private Limited is a 60-unit BMC-sanctioned project in Parel, Mumbai 400012, launched in August 2017; its MahaRERA registration has lapsed. 58 units booked out of total 60 units. The concrete structure (RCC) is complete.

Read full summary

Maruti Palatial is a BMC-sanctioned project by Grs Shelters Private Limited in Parel, Mumbai 400012, registered with MahaRERA as P51900008828. It was launched in August 2017. It has 60 units in 3 buildings: 52 homes (1, 2 and 3 BHK) and 8 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2024, after an extension of 1 year from the original December 2023. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 97% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

58 units booked out of total 60 units (97%).