Baug E Umar, Mumbai Central

by Mahanagar Constructions Private Limited · Mumbai Central, Mumbai 400008 · Map

Launched
Aug 20175 yrs 4 mths originally promised
Possession (MahaRERA)
Apr 2027Extended by 4 yrs 4 mths
Concrete structure
0%Early stage
Booked (free sale)
13 of 3142% · 41 rehab units
Buildings
10.1 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale13 booked out of 31 units

Rehab41 units for existing members

Total 72 units. Rehab units are not for sale.

Project facts

1 RK
28
1 BHK
40
Other units
4
Total units
72
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
1
Free-sale units
31
Rehab units
41

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%13
100%0%0%13
100%0%0%–
100%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400008

Projects with 30–150 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400008
MeasureThis projectSimilar projects
Launch to possession (as first promised)5 yrs 4 mths4 yrs 10 mths
Possession date extendedBy 4 yrs 4 mths5 of 6
Possession date (MahaRERA)Apr 2027Aug 2026
Concrete structure (RCC)0%58%
MahaRERA complaints (filed by or against the builder)13

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Baug E Umar by Mahanagar Constructions Private Limited is a 72-unit BMC-sanctioned project in Mumbai Central, Mumbai 400008, launched in August 2017 with possession due in April 2027. 13 units booked out of 31 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Baug E Umar is a BMC-sanctioned project by Mahanagar Constructions Private Limited in Mumbai Central, Mumbai 400008, registered with MahaRERA as P51900007117. It was launched in August 2017. It has 72 units in 1 building: 68 homes (1 RK and 1 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 72 units, 31 are for sale and 41 are rehab units for existing members.

Its registered possession date is April 2027, extended by 4 years 4 months from the original December 2022. Construction: excavation complete, structure (RCC) not started, final finishes not started.

13 units booked out of 31 units for sale (42%).