La Mer Residences, Mumbai Central

by Excellent Realtor Developers · Mumbai Central, Mumbai 400008 · Map

Launched
Aug 20175 yrs 4 mths originally promised
Possession (MahaRERA)
Dec 2030Extended by 8 yrs
Concrete structure
45%Mid-construction
Booked (free sale)
77 of 20138% · 41 rehab units
Buildings
21.4 acres
MahaRERA complaints
14Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale77 booked out of 201 units

Rehab41 units for existing members

Total 242 units. Rehab units are not for sale.

Project facts

2 BHK
66
3 BHK
10
Other units
166
Total units
242
Buildings
2
Land
1.4 acres
Phases
1
MahaRERA complaints
14
Free-sale units
201
Rehab units
41

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)45%
Finishes, lifts and services50%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 7%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 45%Oct 2026: Concrete structure (RCC) 45%Dec 2024: Final finishes 45%Dec 2025: Final finishes 0%Jul 2026: Final finishes 50%Oct 2026: Final finishes 50%Excavation 100%Final finishes 50%Concrete structure (RCC) 45%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%45%50%77
100%45%50%69
100%0%0%69
100%7%45%36

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400008

Projects with 30–200 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400008
MeasureThis projectSimilar projects
Launch to possession (as first promised)5 yrs 4 mths4 yrs 10 mths
Possession date extendedBy 8 yrs5 of 6
Possession date (MahaRERA)Dec 2030Aug 2026
Concrete structure (RCC)45%46%
MahaRERA complaints (filed by or against the builder)141

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

La Mer Residences by Excellent Realtor Developers is a 242-unit BMC-sanctioned project in Mumbai Central, Mumbai 400008, launched in August 2017 with possession due in December 2030. 77 units booked out of 201 units for sale. The concrete structure (RCC) is 45% complete.

Read full summary

La Mer Residences is a BMC-sanctioned project by Excellent Realtor Developers in Mumbai Central, Mumbai 400008, registered with MahaRERA as P51900004434. It was launched in August 2017. It has 242 units in 2 buildings: 76 homes (2 and 3 BHK) and 166 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 242 units, 201 are for sale and 41 are rehab units for existing members.

Its registered possession date is December 2030, extended by 8 years from the original December 2022. Construction: excavation complete, structure (RCC) 45% complete, final finishes 50% complete.

77 units booked out of 201 units for sale (38%). Since the July 2026 update, 8 more units have been booked and the possession date has moved from December 2027 to December 2030.