Emmanuel, Dadar West
by Skyline Realty Private Limited · Dadar West, Mumbai 400028 · Map
- Launched
- Mar 20214 yrs 9 mths originally promised
- Possession (MahaRERA)
- Dec 2026Extended by 1 yr
- Concrete structure
- 89%Mid-construction
- Booked (free sale)
- 52 of 52100% · 11 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale52 booked out of 52 units
Rehab11 units for existing members
Land-owner share4 units, not for sale
Total 67 units. Rehab and land-owner units are not for sale.
Project facts
- 1 BHK
- 60
- 2 BHK
- 6
- 3 BHK
- 1
- Total units
- 67
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 52
- Rehab units
- 11
- Land-owner share (not for sale)
- 4
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 89% | 25% | 52 | |
| 100% | 89% | 10% | 51 | |
| 100% | 87% | 0% | 0 | |
| 100% | 87% | 0% | 56 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400028
Projects with 30–150 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs 9 mths | 3 yrs 6 mths |
| Possession date extended | By 1 yr | 2 of 3 |
| Possession date (MahaRERA) | Dec 2026 | Sep 2026 |
| Concrete structure (RCC) | 89% | 100% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- Skyline, Dadar West
- Park Abode, Dadar West
- Arihant Tower, Dadar West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Skyline | June 2021 | March 2024 | 90% | – |
| Park Abode | June 2021 | January 2027 | 100% | 33 units booked out of 38 units for sale |
| Arihant Tower | October 2021 | September 2026 | 100% | 16 units booked out of 33 units for sale |
About this project
Emmanuel by Skyline Realty Private Limited is a 67-unit BMC-sanctioned project in Dadar West, Mumbai 400028, launched in March 2021 with possession due in December 2026. 52 units booked out of 52 units for sale. The concrete structure (RCC) is 89% complete.
Read full summary
Emmanuel is a BMC-sanctioned project by Skyline Realty Private Limited in Dadar West, Mumbai 400028, registered with MahaRERA as P51900028729. It was launched in March 2021. It has 67 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 67 units, 52 are for sale, 11 are rehab units for existing members and 4 are the land-owner's share, not for sale.
Its registered possession date is December 2026, extended by 1 year from the original December 2025. Construction: excavation complete, structure (RCC) 89% complete, final finishes 25% complete.
52 units booked out of 52 units for sale (100%). Since the July 2026 update, 1 more unit has been booked.