Park Abode, Dadar West
Ready to move
by Shree Siddhivinayak Developer · Dadar West, Mumbai 400028 · Map
- Launched
- Jun 20213 yrs 6 mths originally promised
- Possession (MahaRERA)
- Jan 2027Extended by 2 yrs 1 mth
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 33 of 3887% · 50 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale33 booked out of 38 units
Rehab50 units for existing members
Total 88 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 37
- 2 BHK
- 35
- 3 BHK
- 5
- 4 BHK
- 1
- 5+ BHK
- 1
- Other units
- 9
- Total units
- 88
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 38
- Rehab units
- 50
- Reserved units
- 4
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 33 | |
| 100% | 100% | 90% | 26 | |
| 100% | 100% | 87% | 19 | |
| 100% | 100% | 65% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 5 similar projects in PIN 400028
Projects with 30–200 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 6 mths | 3 yrs 4 mths |
| Possession date extended | By 2 yrs 1 mth | 4 of 5 |
| Possession date (MahaRERA) | Jan 2027 | Sep 2026 |
| Concrete structure (RCC) | 100% | 90% |
| Units booked (free sale) | 87% | 56% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 5 projects
- Skyline, Dadar West
- Emmanuel, Dadar West
- Arihant Tower, Dadar West
- Meraki, Dadar West
- Ratan Address, Dadar West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Skyline | June 2021 | March 2024 | 90% | – |
| Emmanuel | March 2021 | December 2026 | 89% | 52 units booked out of 52 units for sale |
| Arihant Tower | October 2021 | September 2026 | 100% | 16 units booked out of 33 units for sale |
| Meraki | November 2021 | December 2025 | 22% | 10 units booked out of 24 units for sale |
| Ratan Address | February 2022 | January 2027 | 100% | 29 units booked out of 45 units for sale |
About this project
Park Abode by Shree Siddhivinayak Developer is an 88-unit BMC-sanctioned project in Dadar West, Mumbai 400028, launched in June 2021 with possession due in January 2027. 33 units booked out of 38 units for sale. The concrete structure (RCC) is complete.
Read full summary
Park Abode is a BMC-sanctioned project by Shree Siddhivinayak Developer in Dadar West, Mumbai 400028, registered with MahaRERA as P51900029734. It was launched in June 2021. It has 88 units in 1 building: 79 homes (1, 2, 3, 4 and 5+ BHK) and 9 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 88 units, 38 are for sale and 50 are rehab units for existing members.
Its registered possession date is January 2027, extended by 2 years 1 month from the original December 2024. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.
33 units booked out of 38 units for sale (87%). Since the July 2026 update, 7 more units have been booked and the possession date has moved from December 2025 to January 2027.