- Launched
- Jun 20211 yr 9 mths originally promised
- Possession (MahaRERA)
- Mar 2024Extended by 1 yrWhat does Lapsed mean?
- Concrete structure
- 90%Mid-construction
- Booked
- –
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 RK
- 1
- 1 BHK
- 57
- 2 BHK
- 4
- Other units
- 1
- Total units
- 63
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 90% | 40% | – | |
| 100% | 90% | 40% | – | |
| 100% | 90% | 40% | 53 |
"–" means MahaRERA shows no figure for that update.
Compared with 5 similar projects in PIN 400028
Projects with 30–150 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 1 yr 9 mths | 3 yrs 6 mths |
| Possession date extended | By 1 yr | 4 of 5 |
| Possession date (MahaRERA) | Mar 2024 | Dec 2026 |
| Concrete structure (RCC) | 90% | 100% |
| Units booked | – | 64% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 5 projects
- Park Abode, Dadar West
- Emmanuel, Dadar West
- Arihant Tower, Dadar West
- Meraki, Dadar West
- Ratan Address, Dadar West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Park Abode | June 2021 | January 2027 | 100% | 33 units booked out of 38 units for sale |
| Emmanuel | March 2021 | December 2026 | 89% | 52 units booked out of 52 units for sale |
| Arihant Tower | October 2021 | September 2026 | 100% | 16 units booked out of 33 units for sale |
| Meraki | November 2021 | December 2025 | 22% | 10 units booked out of 24 units for sale |
| Ratan Address | February 2022 | January 2027 | 100% | 29 units booked out of 45 units for sale |
About this project
Skyline by Arihant Builders And Developers is a 63-unit project in Dadar West, Mumbai 400028, launched in June 2021; its MahaRERA registration has lapsed. The concrete structure (RCC) is 90% complete.
Read full summary
Skyline is a project by Arihant Builders And Developers in Dadar West, Mumbai 400028, registered with MahaRERA as P51900029610. It was launched in June 2021. It has 63 units in 1 building: 62 homes (1 RK, 1 BHK and 2 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in March 2024, after an extension of 1 year from the original March 2023. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 90% complete, final finishes 40% complete.