- Launched
- Feb 20222 yrs 2 mths originally promised
- Possession (MahaRERA)
- Jan 2027Extended by 2 yrs 9 mths
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 29 of 4564% · 98 rehab units
- Buildings
- 10.4 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale29 booked out of 45 units
Rehab98 units for existing members
Total 143 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 37
- 2 BHK
- 59
- 3 BHK
- 29
- Other units
- 18
- Total units
- 143
- Buildings
- 1
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 45
- Rehab units
- 98
- Reserved units
- 2
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 29 | |
| 100% | 100% | 100% | 25 | |
| 100% | 100% | 91% | 25 | |
| 100% | 85% | 15% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400028
Projects with 60–250 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 2 mths | 3 yrs 6 mths |
| Possession date extended | By 2 yrs 9 mths | 2 of 3 |
| Possession date (MahaRERA) | Jan 2027 | Sep 2026 |
| Concrete structure (RCC) | 100% | 100% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- Arihant Tower, Dadar West
- Park Abode, Dadar West
- Skyline, Dadar West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Arihant Tower | October 2021 | September 2026 | 100% | 16 units booked out of 33 units for sale |
| Park Abode | June 2021 | January 2027 | 100% | 33 units booked out of 38 units for sale |
| Skyline | June 2021 | March 2024 | 90% | – |
About this project
Ratan Address by Shri Nakoda Enterprises is a 143-unit BMC-sanctioned project in Dadar West, Mumbai 400028, launched in February 2022 with possession due in January 2027. 29 units booked out of 45 units for sale. The concrete structure (RCC) is complete.
Read full summary
Ratan Address is a BMC-sanctioned project by Shri Nakoda Enterprises in Dadar West, Mumbai 400028, registered with MahaRERA as P51900032985. It was launched in February 2022. It has 143 units in 1 building: 125 homes (1, 2 and 3 BHK) and 18 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 143 units, 45 are for sale and 98 are rehab units for existing members.
Its registered possession date is January 2027, extended by 2 years 9 months from the original April 2024. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.
29 units booked out of 45 units for sale (64%). Since the July 2026 update, 4 more units have been booked and the possession date has moved from April 2025 to January 2027.