Vijayshree, Dadar West

by Sugee Eighteen Developers LLP · Dadar West, Mumbai 400028 · Map

Launched
Sep 20233 yrs promised
Possession (MahaRERA)
Sep 2026Not extended
Concrete structure
82%Mid-construction
Booked (free sale)
7 of 978% · 24 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale7 booked out of 9 units

Rehab24 units for existing members

Total 33 units. Rehab units are not for sale.

Project facts

1 RK
1
1 BHK
12
3 BHK
18
4 BHK
1
5+ BHK
1
Total units
33
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
9
Rehab units
24

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)82%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 82%Jul 2026: Concrete structure (RCC) 82%Oct 2026: Concrete structure (RCC) 82%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 82%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%82%0%7
100%82%0%–
100%82%0%–
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400028

Projects with 10–70 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400028
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs3 yrs 6 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Sep 2026Jun 2027
Concrete structure (RCC)82%92%
Units booked (free sale)78%62%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Vijayshree by Sugee Eighteen Developers LLP is a 33-unit BMC-sanctioned project in Dadar West, Mumbai 400028, launched in September 2023 with possession due in September 2026. 7 units booked out of 9 units for sale. The concrete structure (RCC) is 82% complete.

Read full summary

Vijayshree is a BMC-sanctioned project by Sugee Eighteen Developers LLP in Dadar West, Mumbai 400028, registered with MahaRERA as P51900052518. It was launched in September 2023. It has 33 units in 1 building, with 1 RK, 1 BHK, 3 BHK, 4 BHK and 5+ BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 33 units, 9 are for sale and 24 are rehab units for existing members.

Possession was due in September 2026. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) 82% complete, final finishes not started.

7 units booked out of 9 units for sale (78%).