Skip to main content

Oceana, Dadar West

by Kohinoor Planet Constructions Pvt Ltd · Dadar West, Mumbai 400028 · Map

Launched
Oct 20235 yrs 2 mths promised
Possession (MahaRERA)
Dec 2028Not extended
Concrete structure
5%Mid-construction
Booked (free sale)
5 of 683% · 20 rehab units
Buildings
10.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale5 booked out of 6 units

Rehab20 units for existing members

Total 26 units. Rehab units are not for sale.

Project facts

3 BHK
12
4 BHK
13
Other units
1
Total units
26
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
0
Free-sale units
6
Rehab units
20

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)5%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 80%Dec 2025: Excavation 80%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 5%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 5%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%5%0%5
100%0%0%5
80%0%0%5
80%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400028

Projects with 10–50 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 400028
MeasureThis projectSimilar projects
Launch to possession (as first promised)5 yrs 2 mths3 yrs
Possession date extendedNo0 of 5
Possession date (MahaRERA)Dec 2028Dec 2026
Concrete structure (RCC)5%100%
Units booked (free sale)83%78%
MahaRERA complaints (filed by or against the builder)00

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Oceana by Kohinoor Planet Constructions Pvt Ltd is a 26-unit BMC-sanctioned project in Dadar West, Mumbai 400028, launched in October 2023 with possession due in December 2028. 5 units booked out of 6 units for sale. The concrete structure (RCC) is 5% complete.

Read full summary

Oceana is a BMC-sanctioned project by Kohinoor Planet Constructions Pvt Ltd in Dadar West, Mumbai 400028, registered with MahaRERA as P51900053437. It was launched in October 2023. It has 26 units in 1 building: 25 homes (3 and 4 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 26 units, 6 are for sale and 20 are rehab units for existing members.

Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 5% complete, final finishes not started.

5 units booked out of 6 units for sale (83%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 5%.