Mangesh Residency, Dadar West

by Tendulkar And Associates · Dadar West, Mumbai 400028 · Map

Launched
Sep 20234 yrs 3 mths promised
Possession (MahaRERA)
Dec 2027Not extended
Concrete structure
65%Mid-construction
Booked (free sale)
4 of 3212% · 18 rehab units
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale4 booked out of 32 units

Rehab18 units for existing members

Land-owner share1 unit, not for sale

Total 51 units. Rehab and land-owner units are not for sale.

Project facts

1 BHK
39
3 BHK
11
Other units
1
Total units
51
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
32
Rehab units
18
Land-owner share (not for sale)
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)65%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 35%Jul 2026: Concrete structure (RCC) 60%Oct 2026: Concrete structure (RCC) 65%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 65%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%65%0%4
100%60%0%3
100%35%0%2
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400028

Projects with 20–100 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400028
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 3 mths3 yrs 2 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Dec 2027Dec 2026
Concrete structure (RCC)65%92%
Units booked (free sale)12%81%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Mangesh Residency by Tendulkar And Associates is a 51-unit BMC-sanctioned project in Dadar West, Mumbai 400028, launched in September 2023 with possession due in December 2027. 4 units booked out of 32 units for sale. The concrete structure (RCC) is 65% complete.

Read full summary

Mangesh Residency is a BMC-sanctioned project by Tendulkar And Associates in Dadar West, Mumbai 400028, registered with MahaRERA as P51900052706. It was launched in September 2023. It has 51 units in 1 building: 50 homes (1 and 3 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 51 units, 32 are for sale, 18 are rehab units for existing members and 1 is the land-owner's share, not for sale.

Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 65% complete, final finishes not started.

4 units booked out of 32 units for sale (12%). Since the July 2026 update, 1 more unit has been booked and the reported concrete structure (RCC) has gone from 60% to 65%.