- Launched
- Jan 20242 yrs 11 mths promised
- Possession (MahaRERA)
- Dec 2026Not extended
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 15 of 1883% · 5 rehab units
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale15 booked out of 18 units
Rehab5 units for existing members
Land-owner share7 units, not for sale
Total 30 units. Rehab and land-owner units are not for sale.
Project facts
- 1 RK
- 3
- 1 BHK
- 4
- 2 BHK
- 23
- Total units
- 30
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 18
- Rehab units
- 5
- Land-owner share (not for sale)
- 7
- Reserved units
- 4
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 15 | |
| 100% | 100% | 100% | 15 | |
| 100% | 100% | 50% | 13 | |
| 10% | 30% | 5% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 5 similar projects in PIN 400028
Projects with 10–60 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 11 mths | 3 yrs |
| Possession date extended | No | 1 of 5 |
| Possession date (MahaRERA) | Dec 2026 | Jun 2027 |
| Concrete structure (RCC) | 100% | 82% |
| Units booked (free sale) | 83% | 70% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 5 projects
- Park 55, Dadar West
- Oceana, Dadar West
- Buildarch Sakura, Dadar West
- Vijayshree, Dadar West
- Mangesh Residency, Dadar West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Park 55 | January 2024 | December 2026 | 100% | 7 units booked out of 18 units for sale |
| Oceana | October 2023 | December 2028 | 5% | 5 units booked out of 6 units for sale |
| Buildarch Sakura | April 2024 | June 2027 | 95% | 14 units booked out of 20 units for sale |
| Vijayshree | September 2023 | September 2026 | 82% | 7 units booked out of 9 units for sale |
| Mangesh Residency | September 2023 | December 2027 | 65% | 4 units booked out of 32 units for sale |
About this project
Unique Serenity by Uct Ventures LLP is a 30-unit BMC-sanctioned project in Dadar West, Mumbai 400028, launched in January 2024 with possession due in December 2026. 15 units booked out of 18 units for sale. The concrete structure (RCC) is complete.
Read full summary
Unique Serenity is a BMC-sanctioned project by Uct Ventures LLP in Dadar West, Mumbai 400028, registered with MahaRERA as P51900054340. It was launched in January 2024. It has 30 units in 1 building, with 1 RK, 1 BHK and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 30 units, 18 are for sale, 5 are rehab units for existing members and 7 are the land-owner's share, not for sale.
Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.
15 units booked out of 18 units for sale (83%).