Krishna Kunj, Dadar East
by Endemic Properties LLP · Dadar East, Mumbai 400014 · Map
- Launched
- Jan 20254 yrs 8 mths promised
- Possession (MahaRERA)
- Sep 2029Not extended
- Concrete structure
- 94%Mid-construction
- Booked (free sale)
- 12 of 1771% · 8 rehab units
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale12 booked out of 17 units
Rehab8 units for existing members
Total 25 units. Rehab units are not for sale.
Project facts
- 1 RK
- 1
- 1 BHK
- 3
- 2 BHK
- 15
- 3 BHK
- 1
- 4 BHK
- 1
- Other units
- 4
- Total units
- 25
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 17
- Rehab units
- 8
- Reserved units
- 4
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 94% | 0% | 12 | |
| 100% | 0% | 0% | 9 | |
| 100% | 0% | 0% | 9 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400014
Projects with 10–50 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs 8 mths | 3 yrs 9 mths |
| Possession date extended | No | 0 of 4 |
| Possession date (MahaRERA) | Sep 2029 | Sep 2028 |
| Concrete structure (RCC) | 94% | 50% |
| Units booked (free sale) | 71% | 44% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 4 projects
- Siddhgiri, Dadar East
- Ekta Vistabella, Dadar East
- Sanghvi Optima, Dadar East
- Sugee Srushti, Dadar East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Siddhgiri | March 2025 | December 2028 | 70% | 4 units booked out of 9 units for sale |
| Ekta Vistabella | March 2025 | December 2028 | 31% | 3 units booked out of 16 units for sale |
| Sanghvi Optima | August 2024 | May 2028 | 0% | – |
| Sugee Srushti | July 2024 | October 2027 | 83% | 12 units booked out of total 18 units |
About this project
Krishna Kunj by Endemic Properties LLP is a 25-unit BMC-sanctioned project in Dadar East, Mumbai 400014, launched in January 2025 with possession due in September 2029. 12 units booked out of 17 units for sale. The concrete structure (RCC) is 94% complete.
Read full summary
Krishna Kunj is a BMC-sanctioned project by Endemic Properties LLP in Dadar East, Mumbai 400014, registered with MahaRERA as P51900078747. It was launched in January 2025. It has 25 units in 1 building: 21 homes (1 RK, 1 BHK, 2 BHK, 3 BHK and 4 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 25 units, 17 are for sale and 8 are rehab units for existing members.
Its registered possession date is September 2029, unchanged since launch. Construction: excavation complete, structure (RCC) 94% complete, final finishes not started.
12 units booked out of 17 units for sale (71%). Since the July 2026 update, 3 more units have been booked and the reported concrete structure (RCC) has gone from 0% to 94%.