Ekta Vistabella, Dadar East

by Ekta Shelters Private Limited · Dadar East, Mumbai 400014 · Map

Launched
Mar 20253 yrs 9 mths promised
Possession (MahaRERA)
Dec 2028Not extended
Concrete structure
31%Mid-construction
Booked (free sale)
3 of 1619%
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale3 booked out of 16 units

Land-owner share12 units, not for sale

Total 28 units. Land-owner units are not for sale.

Project facts

1 BHK
1
2 BHK
2
3 BHK
21
4 BHK
2
5+ BHK
2
Total units
28
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
16
Land-owner share (not for sale)
12

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)31%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 31%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 31%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%31%0%3
100%0%0%3
100%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400014

Projects with 10–60 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400014
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 9 mths3 yrs 6 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Dec 2028Dec 2028
Concrete structure (RCC)31%97%
Units booked (free sale)19%52%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Ekta Vistabella by Ekta Shelters Private Limited is a 28-unit BMC-sanctioned project in Dadar East, Mumbai 400014, launched in March 2025 with possession due in December 2028. 3 units booked out of 16 units for sale. The concrete structure (RCC) is 31% complete.

Read full summary

Ekta Vistabella is a BMC-sanctioned project by Ekta Shelters Private Limited in Dadar East, Mumbai 400014, registered with MahaRERA as P51900079841. It was launched in March 2025. It has 28 units in 1 building, with 1, 2, 3, 4 and 5+ BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 28 units, 16 are for sale and 12 are the land-owner's share, not for sale.

Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 31% complete, final finishes not started.

3 units booked out of 16 units for sale (19%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 31%.