Siddhgiri, Dadar East

by Baf Na Properties LLP · Dadar East, Mumbai 400014 · Map

Launched
Mar 20253 yrs 9 mths promised
Possession (MahaRERA)
Dec 2028Not extended
Concrete structure
70%Mid-construction
Booked (free sale)
4 of 944% · 11 rehab units
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale4 booked out of 9 units

Rehab11 units for existing members

Total 20 units. Rehab units are not for sale.

Project facts

1 BHK
2
2 BHK
2
3 BHK
15
Other units
1
Total units
20
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
9
Rehab units
11

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)70%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 0%Jul 2026: Excavation 0%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 70%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 70%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%70%0%4
0%0%0%0
0%0%0%–

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400014

Projects with up to 40 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400014
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 9 mths4 yrs 2 mths
Possession date extendedNo0 of 4
Possession date (MahaRERA)Dec 2028Mar 2029
Concrete structure (RCC)70%97%
Units booked (free sale)44%44%
MahaRERA complaints (filed by or against the builder)00

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Siddhgiri by Baf Na Properties LLP is a 20-unit BMC-sanctioned project in Dadar East, Mumbai 400014, launched in March 2025 with possession due in December 2028. 4 units booked out of 9 units for sale. The concrete structure (RCC) is 70% complete.

Read full summary

Siddhgiri is a BMC-sanctioned project by Baf Na Properties LLP in Dadar East, Mumbai 400014, registered with MahaRERA as P51800079558. It was launched in March 2025. It has 20 units in 1 building: 19 homes (1, 2 and 3 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 20 units, 9 are for sale and 11 are rehab units for existing members.

Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 70% complete, final finishes not started.

4 units booked out of 9 units for sale (44%). Since the July 2026 update, 4 more units have been booked and the reported concrete structure (RCC) has gone from 0% to 70%.