Shreeji Serenity, Dadar East
by Space Infra · Dadar East, Mumbai 400014 · Map
- Launched
- Feb 20253 yrs 1 mth promised
- Possession (MahaRERA)
- Mar 2028Not extended
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 16 of 2759% · 40 rehab units
- Buildings
- 20.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale16 booked out of 27 units
Rehab40 units for existing members
Total 67 units. Rehab units are not for sale.
Project facts
- 1 RK
- 1
- 1 BHK
- 43
- 2 BHK
- 10
- 3 BHK
- 5
- Other units
- 8
- Total units
- 67
- Buildings
- 2
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 27
- Rehab units
- 40
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 60% | 16 | |
| 100% | 76% | 0% | 11 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400014
Projects with 20–150 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 1 mth | 3 yrs 3 mths |
| Possession date extended | No | 0 of 3 |
| Possession date (MahaRERA) | Mar 2028 | Dec 2028 |
| Concrete structure (RCC) | 100% | 31% |
| Units booked (free sale) | 59% | 0% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- Ekta Vistabella, Dadar East
- Satviki Horizon, Dadar East
- Najamai Mansion, Dadar East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Ekta Vistabella | March 2025 | December 2028 | 31% | 3 units booked out of 16 units for sale |
| Satviki Horizon | July 2025 | July 2028 | 0% | 0 units booked out of 16 units for sale |
| Najamai Mansion | September 2025 | December 2028 | 100% | 0 units booked out of 24 units for sale |
About this project
Shreeji Serenity by Space Infra is a 67-unit BMC-sanctioned project in Dadar East, Mumbai 400014, launched in February 2025 with possession due in March 2028. 16 units booked out of 27 units for sale. The concrete structure (RCC) is complete.
Read full summary
Shreeji Serenity is a BMC-sanctioned project by Space Infra in Dadar East, Mumbai 400014, registered with MahaRERA as P51900079259. It was launched in February 2025. It has 67 units in 2 buildings: 59 homes (1 RK, 1 BHK, 2 BHK and 3 BHK) and 8 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 67 units, 27 are for sale and 40 are rehab units for existing members.
Its registered possession date is March 2028, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 60% complete.
16 units booked out of 27 units for sale (59%). Since the July 2026 update, 5 more units have been booked and the reported concrete structure (RCC) has gone from 76% to 100%.