Satviki Horizon, Dadar East

by Satviki Realty · Dadar East, Mumbai 400014 · Map

Launched
Jul 20253 yrs promised
Possession (MahaRERA)
Jul 2028Not extended
Concrete structure
0%Early stage
Booked (free sale)
0 of 160% · 57 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale0 booked out of 16 units

Rehab57 units for existing members

Total 73 units. Rehab units are not for sale.

Project facts

1 BHK
18
2 BHK
27
3 BHK
10
4 BHK
2
Other units
16
Total units
73
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
16
Rehab units
57

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 95%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%0
100%0%0%0
95%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400014

Projects with 20–150 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 400014
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs3 yrs 3 mths
Possession date extendedNo0 of 3
Possession date (MahaRERA)Jul 2028Dec 2028
Concrete structure (RCC)0%100%
Units booked (free sale)0%19%
MahaRERA complaints (filed by or against the builder)00

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Satviki Horizon by Satviki Realty is a 73-unit BMC-sanctioned project in Dadar East, Mumbai 400014, launched in July 2025 with possession due in July 2028. 0 units booked out of 16 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Satviki Horizon is a BMC-sanctioned project by Satviki Realty in Dadar East, Mumbai 400014, registered with MahaRERA as PM1170002500359. It was launched in July 2025. It has 73 units in 1 building: 57 homes (1, 2, 3 and 4 BHK) and 16 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 73 units, 16 are for sale and 57 are rehab units for existing members.

Its registered possession date is July 2028, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.

0 units booked out of 16 units for sale (0%).