Najamai Mansion, Dadar East

by Navroze Enterprises · Dadar East, Mumbai 400014 · Map

Launched
Sep 20253 yrs 3 mths promised
Possession (MahaRERA)
Dec 2028Not extended
Concrete structure
100%Nearing possession
Booked (free sale)
0 of 240% · 13 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale0 booked out of 24 units

Rehab13 units for existing members

Total 37 units. Rehab units are not for sale.

Project facts

1 RK
8
1 BHK
1
2 BHK
17
3 BHK
3
4 BHK
8
Total units
37
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
24
Rehab units
13

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services60%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2025: Final finishes 0%Jul 2026: Final finishes 60%Oct 2026: Final finishes 60%Excavation 100%Concrete structure (RCC) 100%Final finishes 60%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%60%0
100%100%60%0
100%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400014

Projects with 10–80 flats, launched within 1 year of this one.

Compared with 4 similar projects in PIN 400014
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 3 mths3 yrs 5 mths
Possession date extendedNo0 of 4
Possession date (MahaRERA)Dec 2028Sep 2028
Concrete structure (RCC)100%50%
Units booked (free sale)0%32%
MahaRERA complaints (filed by or against the builder)00

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Najamai Mansion by Navroze Enterprises is a 37-unit BMC-sanctioned project in Dadar East, Mumbai 400014, launched in September 2025 with possession due in December 2028. 0 units booked out of 24 units for sale. The concrete structure (RCC) is complete.

Read full summary

Najamai Mansion is a BMC-sanctioned project by Navroze Enterprises in Dadar East, Mumbai 400014, registered with MahaRERA as PR1170002500682. It was launched in September 2025. It has 37 units in 1 building, with 1 RK, 1 BHK, 2 BHK, 3 BHK and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 37 units, 24 are for sale and 13 are rehab units for existing members.

Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 60% complete.

0 units booked out of 24 units for sale (0%).