Navkar Shatrunjay, Andheri West

by Om Navkar Creators LLP · Andheri West, Mumbai 400058 · Map

Launched
Jul 20253 yrs 1 mth promised
Possession (MahaRERA)
Aug 2028Not extended
Concrete structure
80%Mid-construction
Booked (free sale)
18 of 3355% · 15 rehab units
Buildings
10.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale18 booked out of 33 units

Rehab15 units for existing members

Total 48 units. Rehab units are not for sale.

Project facts

1 BHK
2
2 BHK
4
3 BHK
19
4 BHK
22
5+ BHK
1
Total units
48
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
0
Free-sale units
33
Rehab units
15

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)80%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 70%Oct 2026: Concrete structure (RCC) 80%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 80%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%80%0%18
100%70%0%14
100%0%0%7

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400058

Projects with 20–100 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400058
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 1 mth2 yrs 8 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Aug 2028Dec 2027
Concrete structure (RCC)80%60%
Units booked (free sale)55%33%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Navkar Shatrunjay by Om Navkar Creators LLP is a 48-unit SRA-sanctioned project in Andheri West, Mumbai 400058, launched in July 2025 with possession due in August 2028. 18 units booked out of 33 units for sale. The concrete structure (RCC) is 80% complete.

Read full summary

Navkar Shatrunjay is an SRA-sanctioned project by Om Navkar Creators LLP in Andheri West, Mumbai 400058, registered with MahaRERA as PR1180002500288. It was launched in July 2025. It has 48 units in 1 building, with 1, 2, 3, 4 and 5+ BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 48 units, 33 are for sale and 15 are rehab units for existing members.

Its registered possession date is August 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 80% complete, final finishes not started.

18 units booked out of 33 units for sale (55%). Since the July 2026 update, 4 more units have been booked and the reported concrete structure (RCC) has gone from 70% to 80%.