by Verdent Infra Bultcon · Andheri West, Mumbai 400058 · Map

Launched
Feb 20252 yrs 7 mths promised
Possession (MahaRERA)
Sep 2027Not extended
Concrete structure
0%Early stage
Booked (free sale)
11 of 5022% · 19 rehab units
Buildings
20.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale11 booked out of 50 units

Rehab19 units for existing members

Total 69 units. Rehab units are not for sale.

Project facts

3 BHK
67
Other units
2
Total units
69
Buildings
2
Land
0.4 acres
Phases
1
MahaRERA complaints
0
Free-sale units
50
Rehab units
19

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 0%Jul 2026: Excavation 85%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%11
85%0%0%6
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400058

Projects with 30–150 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400058
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 7 mths2 yrs 11 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Sep 2027Jan 2028
Concrete structure (RCC)0%62%
Units booked (free sale)22%25%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Boston Harbor by Verdent Infra Bultcon is a 69-unit SRA-sanctioned project in Andheri West, Mumbai 400058, launched in February 2025 with possession due in September 2027. 11 units booked out of 50 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Boston Harbor is an SRA-sanctioned project by Verdent Infra Bultcon in Andheri West, Mumbai 400058, registered with MahaRERA as P51800079155. It was launched in February 2025. It has 69 units in 2 buildings: 67 homes (3 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 69 units, 50 are for sale and 19 are rehab units for existing members.

Its registered possession date is September 2027, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.

11 units booked out of 50 units for sale (22%). Since the July 2026 update, 5 more units have been booked.