Sun Sumit Yashodhan, Andheri West
by Sun Sumit Venture · Andheri West, Mumbai 400058 · Map
- Launched
- Mar 20252 yrs 9 mths promised
- Possession (MahaRERA)
- Dec 2027Not extended
- Concrete structure
- 84%Mid-construction
- Booked (free sale)
- 4 of 2218% · 16 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale4 booked out of 22 units
Rehab16 units for existing members
Total 38 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 20
- 2 BHK
- 17
- 3 BHK
- 1
- Total units
- 38
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 22
- Rehab units
- 16
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 84% | 0% | 4 | |
| 100% | 84% | 0% | 4 | |
| 100% | 84% | 0% | 4 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400058
Projects with 10–80 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 9 mths | 2 yrs 8 mths |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | Dec 2027 | Dec 2027 |
| Concrete structure (RCC) | 84% | 40% |
| Units booked (free sale) | 18% | 33% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Boston Harbor, Andheri West
- Parshwa Darshan Phase 1, Andheri West
- Delta Meadows, Andheri West
- Milan Aura, Andheri West
- Navkar Shatrunjay, Andheri West
- Navkar Palace, Andheri West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Boston Harbor | February 2025 | September 2027 | 0% | 11 units booked out of 50 units for sale |
| Parshwa Darshan Phase 1 | April 2025 | December 2027 | 35% | 8 units booked out of 25 units for sale |
| Delta Meadows | December 2024 | June 2027 | 44% | 1 unit booked out of 11 units for sale |
| Milan Aura | July 2025 | December 2027 | 27% | 4 units booked out of 12 units for sale |
| Navkar Shatrunjay | July 2025 | August 2028 | 80% | 18 units booked out of 33 units for sale |
| Navkar Palace | July 2025 | October 2028 | 100% | 26 units booked out of 39 units for sale |
About this project
Sun Sumit Yashodhan by Sun Sumit Venture is a 38-unit BMC-sanctioned project in Andheri West, Mumbai 400058, launched in March 2025 with possession due in December 2027. 4 units booked out of 22 units for sale. The concrete structure (RCC) is 84% complete.
Read full summary
Sun Sumit Yashodhan is a BMC-sanctioned project by Sun Sumit Venture in Andheri West, Mumbai 400058, registered with MahaRERA as P51800079912. It was launched in March 2025. It has 38 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 38 units, 22 are for sale and 16 are rehab units for existing members.
Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 84% complete, final finishes not started.
4 units booked out of 22 units for sale (18%).