Parshwa Darshan Phase 1, Andheri West
by Aarsh Developers · Andheri West, Mumbai 400058 · Map
- Launched
- Apr 20252 yrs 8 mths promised
- Possession (MahaRERA)
- Dec 2027Not extended
- Concrete structure
- 35%Mid-construction
- Booked (free sale)
- 8 of 2532% · 44 rehab units
- Buildings
- 20.6 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale8 booked out of 25 units
Rehab44 units for existing members
Total 69 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 34
- 2 BHK
- 35
- Total units
- 69
- Buildings
- 2
- Land
- 0.6 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 25
- Rehab units
- 44
- Reserved units
- 3
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 35% | 0% | 8 | |
| 100% | 0% | 0% | 5 | |
| 100% | 0% | 0% | 5 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400058
Projects with 30–150 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 8 mths | 2 yrs 8 mths |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | Dec 2027 | Dec 2027 |
| Concrete structure (RCC) | 35% | 62% |
| Units booked (free sale) | 32% | 28% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Sun Sumit Yashodhan, Andheri West
- Boston Harbor, Andheri West
- Navkar Palace, Andheri West
- Navkar Shatrunjay, Andheri West
- Milan Aura, Andheri West
- Delta Meadows, Andheri West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Sun Sumit Yashodhan | March 2025 | December 2027 | 84% | 4 units booked out of 22 units for sale |
| Boston Harbor | February 2025 | September 2027 | 0% | 11 units booked out of 50 units for sale |
| Navkar Palace | July 2025 | October 2028 | 100% | 26 units booked out of 39 units for sale |
| Navkar Shatrunjay | July 2025 | August 2028 | 80% | 18 units booked out of 33 units for sale |
| Milan Aura | July 2025 | December 2027 | 27% | 4 units booked out of 12 units for sale |
| Delta Meadows | December 2024 | June 2027 | 44% | 1 unit booked out of 11 units for sale |
About this project
Parshwa Darshan Phase 1 by Aarsh Developers is a 69-unit BMC-sanctioned project in Andheri West, Mumbai 400058, launched in April 2025 with possession due in December 2027. 8 units booked out of 25 units for sale. The concrete structure (RCC) is 35% complete.
Read full summary
Parshwa Darshan Phase 1 is a BMC-sanctioned project by Aarsh Developers in Andheri West, Mumbai 400058, registered with MahaRERA as P51800080140. It was launched in April 2025. It has 69 units in 2 buildings, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 69 units, 25 are for sale and 44 are rehab units for existing members.
Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 35% complete, final finishes not started.
8 units booked out of 25 units for sale (32%). Since the July 2026 update, 3 more units have been booked and the reported concrete structure (RCC) has gone from 0% to 35%.