Mio Miraya, Bandra West
by Sayaji Realty Private Limited · Bandra West, Mumbai 400050 · Map
- Launched
- Oct 20253 yrs 2 mths promised
- Possession (MahaRERA)
- Dec 2028Not extended
- Concrete structure
- 0%Early stage
- Booked (free sale)
- 3 of 1323% · 31 rehab units
- Buildings
- 10.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale3 booked out of 13 units
Rehab31 units for existing members
Total 44 units. Rehab units are not for sale.
Project facts
- 1 RK
- 1
- 1 BHK
- 2
- 2 BHK
- 27
- 3 BHK
- 14
- Total units
- 44
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 13
- Rehab units
- 31
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 20% | 0% | 0% | 3 | |
| 20% | 0% | 0% | 3 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400050
Projects with 20–90 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 2 mths | 3 yrs 4 mths |
| Possession date extended | No | 1 of 4 |
| Possession date (MahaRERA) | Dec 2028 | Jan 2029 |
| Concrete structure (RCC) | 0% | 0% |
| Units booked (free sale) | 23% | 42% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 4 projects
- Bandstand Cama, Bandra West
- Paradigm Superstar, Bandra West
- Zahra, Bandra West
- 9 Elements, Bandra West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Bandstand Cama | October 2025 | April 2032 | 0% | 3 units booked out of 25 units for sale |
| Paradigm Superstar | November 2025 | March 2029 | 0% | 0 units booked out of 21 units for sale |
| Zahra | December 2025 | December 2028 | 29% | 15 units booked out of 21 units for sale |
| 9 Elements | May 2025 | October 2028 | 0% | 57 units booked out of 57 units for sale |
About this project
Mio Miraya by Sayaji Realty Private Limited is a 44-unit BMC-sanctioned project in Bandra West, Mumbai 400050, launched in October 2025 with possession due in December 2028. 3 units booked out of 13 units for sale. Work on the concrete structure (RCC) has not started.
Read full summary
Mio Miraya is a BMC-sanctioned project by Sayaji Realty Private Limited in Bandra West, Mumbai 400050, registered with MahaRERA as PR1180002501188. It was launched in October 2025. It has 44 units in 1 building, with 1 RK, 1 BHK, 2 BHK and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 44 units, 13 are for sale and 31 are rehab units for existing members.
Its registered possession date is December 2028, unchanged since launch. Construction: excavation 20% complete, structure (RCC) not started, final finishes not started.
3 units booked out of 13 units for sale (23%).