Paradigm Superstar, Bandra West
by Paradigm Framework LLP · Bandra West, Mumbai 400050 · Map
- Launched
- Nov 20253 yrs 4 mths promised
- Possession (MahaRERA)
- Mar 2029Not extended
- Concrete structure
- 0%Early stage
- Booked (free sale)
- 0 of 210% · 25 rehab units
- Buildings
- 10.3 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale0 booked out of 21 units
Rehab25 units for existing members
Total 46 units. Rehab units are not for sale.
Project facts
- 2 BHK
- 10
- 3 BHK
- 12
- 4 BHK
- 23
- Other units
- 1
- Total units
- 46
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 1
- Free-sale units
- 21
- Rehab units
- 25
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 65% | 0% | 0% | 0 | |
| 35% | 0% | 0% | 0 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 5 similar projects in PIN 400050
Projects with 20–90 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 4 mths | 3 yrs 5 mths |
| Possession date extended | No | 1 of 5 |
| Possession date (MahaRERA) | Mar 2029 | Dec 2028 |
| Concrete structure (RCC) | 0% | 0% |
| Units booked (free sale) | 0% | 23% |
| MahaRERA complaints (filed by or against the builder) | 1 | 0 |
The 5 projects
- Mio Miraya, Bandra West
- Zahra, Bandra West
- Bandstand Cama, Bandra West
- Oceanic, Bandra West
- 9 Elements, Bandra West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Mio Miraya | October 2025 | December 2028 | 0% | 3 units booked out of 13 units for sale |
| Zahra | December 2025 | December 2028 | 29% | 15 units booked out of 21 units for sale |
| Bandstand Cama | October 2025 | April 2032 | 0% | 3 units booked out of 25 units for sale |
| Oceanic | April 2026 | December 2030 | 0% | 3 units booked out of 15 units for sale |
| 9 Elements | May 2025 | October 2028 | 0% | 57 units booked out of 57 units for sale |
About this project
Paradigm Superstar by Paradigm Framework LLP is a 46-unit SRA-sanctioned project in Bandra West, Mumbai 400050, launched in November 2025 with possession due in March 2029. 0 units booked out of 21 units for sale. Work on the concrete structure (RCC) has not started.
Read full summary
Paradigm Superstar is an SRA-sanctioned project by Paradigm Framework LLP in Bandra West, Mumbai 400050, registered with MahaRERA as PR1180002501587. It was launched in November 2025. It has 46 units in 1 building: 45 homes (2, 3 and 4 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 46 units, 21 are for sale and 25 are rehab units for existing members.
Its registered possession date is March 2029, unchanged since launch. Construction: excavation 65% complete, structure (RCC) not started, final finishes not started.
0 units booked out of 21 units for sale (0%).
Paradigm's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 9 |
|---|---|
| Total units across these projects | 5,095 |
| Completed without extending the possession date | 0 |
| Completed after an extension | 1 |
| Lapsed | 0 |
| Under construction | 8 |
| Possession date extended on the builder's application | 2 |
| MahaRERA complaints (filed by or against the builder), all Paradigm projects | 91 (5 of 9 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.