Zahra, Bandra West

by Aplite Venture LLP · Bandra West, Mumbai 400050 · Map

Launched
Dec 20253 yrs promised
Possession (MahaRERA)
Dec 2028Not extended
Concrete structure
29%Mid-construction
Booked (free sale)
15 of 2171% · 9 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale15 booked out of 21 units

Rehab9 units for existing members

Total 30 units. Rehab units are not for sale.

Project facts

1 BHK
16
2 BHK
4
3 BHK
8
Other units
2
Total units
30
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
21
Rehab units
9
Reserved units
14

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)29%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 0%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 29%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 29%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%29%0%15
100%0%0%15
0%0%0%14

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400050

Projects with 10–60 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400050
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs3 yrs 6 mths
Possession date extendedNo1 of 6
Possession date (MahaRERA)Dec 2028Apr 2029
Concrete structure (RCC)29%0%
Units booked (free sale)71%16%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Zahra by Aplite Venture LLP is a 30-unit SRA-sanctioned project in Bandra West, Mumbai 400050, launched in December 2025 with possession due in December 2028. 15 units booked out of 21 units for sale. The concrete structure (RCC) is 29% complete.

Read full summary

Zahra is an SRA-sanctioned project by Aplite Venture LLP in Bandra West, Mumbai 400050, registered with MahaRERA as PR1180002501647. It was launched in December 2025. It has 30 units in 1 building: 28 homes (1, 2 and 3 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 30 units, 21 are for sale and 9 are rehab units for existing members.

Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 29% complete, final finishes not started.

15 units booked out of 21 units for sale (71%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 29%.