Amarnath Cooperative Housing Society Ltd, Dahisar

by Ankeeta Associates · Dahisar, Mumbai 400068 · Map

Launched
Feb 20261 yr 9 mths promised
Possession (MahaRERA)
Nov 2027Not extended
Concrete structure
45%Mid-construction
Booked (free sale)
2 of 1315% · 16 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale2 booked out of 13 units

Rehab16 units for existing members

Total 29 units. Rehab units are not for sale.

Project facts

1 BHK
10
2 BHK
19
Total units
29
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
13
Rehab units
16

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)45%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jul 2026Oct 2026Jul 2026: Excavation 100%Oct 2026: Excavation 100%Jul 2026: Concrete structure (RCC) 45%Oct 2026: Concrete structure (RCC) 45%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 45%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%45%0%2
100%45%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400068

Projects with 10–60 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400068
MeasureThis projectSimilar projects
Launch to possession (as first promised)1 yr 9 mths2 yrs 8 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Nov 2027Dec 2028
Concrete structure (RCC)45%10%
Units booked (free sale)15%26%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Amarnath Cooperative Housing Society Ltd by Ankeeta Associates is a 29-unit BMC-sanctioned project in Dahisar, Mumbai 400068, launched in February 2026 with possession due in November 2027. 2 units booked out of 13 units for sale. The concrete structure (RCC) is 45% complete.

Read full summary

Amarnath Cooperative Housing Society Ltd is a BMC-sanctioned project by Ankeeta Associates in Dahisar, Mumbai 400068, registered with MahaRERA as PR1180002502308. It was launched in February 2026. It has 29 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 29 units, 13 are for sale and 16 are rehab units for existing members.

Its registered possession date is November 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 45% complete, final finishes not started.

2 units booked out of 13 units for sale (15%). Since the July 2026 update, 2 more units have been booked.