Nivasa projects in Pune

MahaRERA projects by Nivasa registered 2017–2025 in Pune & PCMC.

Projects registered with MahaRERA9
Total units across these projects1,343
Full record

MahaRERA projects registered 2017–2025 in Pune & PCMC

Completed without extending the possession date2
Completed after an extension1
Lapsed1
Under construction5
Possession date extended on the builder's application1
Typical time from launch to 100% structure2 years 4 months
MahaRERA complaints (filed by or against the builder), all Nivasa projects2 (2 of 9 projects)
What these mean
  • Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
  • Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
  • Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
  • Under construction: MahaRERA status Active.
  • Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
  • Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
  • MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.

Where they build: Lohegaon (3) · Mundhwa (1)

Under construction

ProjectVillageStagePossessionBooked
Nivasa Ananya · 2 phasesLohegaonMid-constructionDec 2026 – Dec 2027148 units booked out of total 259 units
Nivasa Elevia · 2 phasesMundhwaNearing possessionDec 2026187 units booked out of total 209 units
Nivasa Enchante · 3 phasesLohegaonMid-constructionMar 2026 – Dec 2027406 units booked out of total 640 units
Completed
ProjectVillageStatus
Nivasa UdaanLohegaonCompleted

Figures as reported to MahaRERA. Projects without a FlatNama page are older or outside the lists; they are named but not linked.

Is a project grouped wrongly or a figure out of date? Tell us