Pride projects in Pune
Every MahaRERA project by Pride in the 59 areas FlatNama covers, registered 2017–2026.
- Registered
- 272017–2026
- Under construction
- 11
- Completed
- 88 without extending
- Complaints
- 12across 11 of 27
Track record
MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers
| Projects registered with MahaRERA | 27 |
|---|---|
| Completed without extending the possession date | 8 |
| Completed after an extension, or lapsed | 8 |
| Under construction | 11 |
| Possession date extended by the builder | 0 |
| Typical time from launch to 100% structure | 2 years 7 months |
| Complaints on MahaRERA, all Pride projects | 12 (11 of 27 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not extend its possession date. MahaRERA's COVID extensions (6 + 6 months, 2020–21) are not counted as the builder's.
- Completed after an extension, or lapsed: every other registration that is not under construction.
- Under construction: MahaRERA status Active.
- Possession date extended by the builder: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure reached 100% between December 2023 and July 2026, counted from registration.
- Complaints: complaints on MahaRERA filed by or against the builder, on all its projects.
Where they build: Charholi (9) · Marunji (9) · Wakad (1)
Under construction (11)
| Project | Village | Stage | Possession | Booked |
|---|---|---|---|---|
| Miami A1, A2, A3, B2 | Charholi | Early stage | December 2029 | |
| Miami A4-A5 | Charholi | Mid-construction | December 2029 | 155 of 270 booked (57%) |
| Miami A6-A7-B1 | Charholi | Mid-construction | December 2028 | 324 of 408 booked (79%) |
| Park Astra Phase II | Marunji | Nearing possession | December 2026 | 127 of 136 booked (93%) |
| Park Titan Phase III | Marunji | Mid-construction | June 2027 | 359 of 411 booked (87%) |
| Park Titan Phase IV | Marunji | Mid-construction | March 2028 | 120 of 239 booked (50%) |
| Park Titan Phase V | Marunji | Early stage | August 2029 | |
| Wellington C - D | Charholi | Finishing stage | September 2026 | 259 of 264 booked (98%) |
| Wellington F-G | Charholi | Nearing possession | December 2027 | 267 of 270 booked (99%) |
| Wellington-e-h-j-k | Charholi | Nearing possession | December 2027 | 523 of 540 booked (97%) |
| Wellington-l-m | Charholi | Finishing stage | September 2026 | 258 of 264 booked (98%) |
Completed (8)
| Project | Village | Stage | Possession | Booked |
|---|---|---|---|---|
| Manhattan | ||||
| Park Astra Phase III | Marunji | Ready to move | June 2026 | 106 of 129 booked (82%) |
| Park Connect | Marunji | Ready to move | December 2023 | 549 of 559 booked (98%) |
| Park Connect Phase II | Marunji | Ready to move | December 2024 | 247 of 272 booked (91%) |
| Park Landmark Phase I | ||||
| Park Landmark Phase II | ||||
| Park Titanium Phase II | Wakad | Ready to move | October 2023 | 185 of 188 booked (98%) |
| Wellington- A-B |
Lapsed (8)
| Project | Village | Stage | Possession | Booked |
|---|---|---|---|---|
| Atlantic | ||||
| Manhattan-e Building | Charholi | Nearing possession | December 2024 | 117 of 122 booked (96%) |
| Park Astra | Nearing possession | December 2025 | 405 of 408 booked (99%) | |
| Park Landmark Phase III | Finishing stage | December 2025 | 105 of 124 booked (85%) | |
| Park Titan | Marunji | Mid-construction | June 2026 | 399 of 412 booked (97%) |
| Park Titan Phase II | Marunji | Nearing possession | June 2026 | 132 of 137 booked (96%) |
| Soho | Charholi | Finishing stage | April 2026 | All 363 units booked |
| Wellington- N-O |
Figures as reported to MahaRERA. Projects without a FlatNama page are older or outside the lists; they are named but not linked.