Skip to main content
← Back

Park Landmark Phase III, Gultekdi

Finishing stageLapsed

Final finishes 95% · completion not yet filed on MahaRERA

by Pride Purple Landmark LLP. Gultekdi, Pune 411037. View on Google Maps

Launched
3 years 2 months promised
Possession date (MahaRERA)
10 months ago. No extension recordedPossession date unchanged since launch. What "Lapsed" means
Concrete structure (RCC)
100%Finishing stageAverage across 2 buildings
Units booked
105 of 12485% booked

Project facts

2 BHK49
3 BHK51
4 BHK24
Total units124
Buildings2
Land0.6 acres
Complaints on MahaRERA (filed by or against the builder)0
Share on WhatsApp

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the promised 3 years 2 months have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 100%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 100%Jun 2024: Concrete structure (RCC) 100%Dec 2024: Concrete structure (RCC) 100%Jun 2025: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 0%Jun 2024: Final finishes 25%Dec 2024: Final finishes 95%Jun 2025: Final finishes 95%Dec 2025: Final finishes 95%Jul 2026: Final finishes 95%Excavation 100%Concrete structure (RCC) 100%Final finishes 95%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%95%105
100%100%25%42
100%100%0%42

"—" means MahaRERA shows no figure for that update.

About this project

Park Landmark Phase III (MahaRERA P52100047206) is a residential project by Pride Purple Landmark LLP in Gultekdi, Pune 411037. It was launched in October 2022. It has 124 units in 2 buildings, with 2, 3 & 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2025. That date has passed and no extension has been recorded. Construction, averaged across its 2 buildings: excavation complete, structure (RCC) complete, final finishes 95% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

105 of its 124 units are booked (85%).

Pride's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA27
Completed without extending the possession date8
Completed after an extension, or lapsed8
Under construction11
Possession date extended by the builder0
Typical time from launch to 100% structure2 years 7 months
Complaints on MahaRERA, all Pride projects12 (11 of 27 projects)

See all Pride projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100047206.Check it on MahaRERA (P52100047206)All projects in Gultekdi, Bibwewadi